Framing has started! With most of the family sick with colds, including myself, I got 8 days to work on the first half of the structure, the low bay side with the attic workshop. My goal was to get the attic subfloor down and a tarp pulled over it before we get any weather. I got lucky really, a string of calm days in the 20s with little wind. Photos to follow on Monday when I'm back at work.
Dec 27th. Marked out three 12ft sill plates for anchor bolts, service penetrations and stud locations.Framed out the left wall in two 12 ft sections, and the left half of the back wall. Left wall has two doors to deal with, and a window.
Dec 28th. Added as much sheathing as possible to square the walls up, grabbed the in-laws and stood the back wall and rear section of the side wall up, nailed my first corner together. Added bracing to keep it square, piles of lumber are still big enough to use as immovable objects to brace too.
Dec 29th. Had to do a little reset, my corner was a little off due to a long stud, so out came the sawzall for a quick fix to get the top plates level. Stood up the front left side wall and got that braced plumb, then added my double top plates all around.
Dec 30th. Built up a header out of 3 2x12s for the left door. The front 2x12 is short to allow the header to be connected across the front of the garage to the header for the right door for more strength later. Framed out the posts either side, leveling my concrete on the left to the top of the steel baseplate on the the center pier with a water tube level. It was 20 degrees, so I used washer fluid. Squared the wall up and called it a day.
Dec 31st. Easy day. Lifted the garage door section into place, nailed the corner, braced it plumb and headed to the home depot for joists hangers and deck screws.
Jan 1st. Installed a 20 ft double 2x12 nailer in the web of the steel beam, bolted into place with 5" bolts. Installed my joists hangers, then cut my 24ft doug fir 2x8 joists in half, and lifted them into place. Hard work for one guy, I was beat by dark.
Jan 2nd. Glued the double 2x8 joists, nailed them, and set them in position. Got all the full length ones in by the end of the day. Coldest day so far, and I was out of toe warmers. Remedied this in the evening. Got 3 pieces of plywood installed as darkness fell and forced me to pack up.
Jan 3rd. Installed the header from the last joist on the steel to the back wall. This is about 2.5 feet in from the steel beam and will serve as the header supporting the stairs. Then installed the last two "short" joists, glued and nailed. Finished up by installing the last 6 pieces of plywood floor, glued and screwed every 8" with 2" deck screws. Cold windy day, and I was flagging from pushing myself the previous day. Hit my head about 8 times on the floor joists.
Some small jobs to do as time permits, need to add the headers for the doorways and window in the left wall, add the sheathing and Tyvek etc. Pulling a tarp over the deck tomorrow as freezing drizzle is in the forecast. So far I've built a pretty nice picnic shelter, but not a bad week's work for a one man crew. Hoping to use a few weekends in January and February to frame the right hand side and 12 ft storage floor out, then get some help in March with the roof framing.
Overall, good progress so far, I'm very happy.
Back to my day job on Monday. Today, I built garages out of jenga blocks with my kids.