Hmmm,
Friday:
Cleanup/prep (masking paper on walls): 1/2 hour
Floor Grinding: 3 hours
Cleanup/pressure washing: 1 hour
Satuday:
Integraflex mixing and expansion joint filling: 1/2 hour
Layer 1 (Bondtite): 3 hours (including prep, cleanup, and breaks between batches, it was hot!)
Sunday:
Layer...