Shop is 32’wx30’ long with existing perimeter footing and a center run footing down the length that seperates the shop in half. This footing is 20” wide, I would be putting the insulation and the slab between the current perimeter footing and the center run. Hard to explain abit but heres a...
For the base of the lift? Thats what bendpak recommends for pouring a base in a cutout in existing concrete so I just thought maybe it would be a good idea to lay out a 12” center grid on the 13.5’x4’ lift section
So I am planning on pouring concrete floor with radiant floor heating and a car lift for my shop with a footing this summer and I just wanted to get some opinions and help on this setup:
Shop is 32’wx30’ long with existing perimeter footing and a center run footing down the length.
This setup...