Recent content by m3jake

  1. M

    2-Post Lift on Post Tension Slab - Permitting After the Fact

    We bought in a new neighborhood (2023) and watched them build probably 30+ homes. From what we saw they did a great job laying out the cables. Fully supported, aligned, and with contours for the bow.
  2. M

    2-Post Lift on Post Tension Slab - Permitting After the Fact

    Amen to that. My city has a 2019 edition that defines what they adopted/amended from the 2018 IRC. So all should be good.
  3. M

    2-Post Lift on Post Tension Slab - Permitting After the Fact

    Little update. The 2024 IRC does have a requirement worth knowing. "R317.7 Automotive Lifts. Where provided, automotive lifts shall be listed and labeled in accordance with ANSI/ALI ALCTV." Mine is not. But, I'm pretty sure my municipality is still on the 2018 IRC which doesn't list that...
  4. M

    2-Post Lift on Post Tension Slab - Permitting After the Fact

    From everything I've read so far I think you're right. Just the electrical part is all I need to worry about. I'm comfortable with that stuff.
  5. M

    2-Post Lift on Post Tension Slab - Permitting After the Fact

    I only know a little. They do engineer the cables with a bow in them so after the cement cures and they tension the cables they help support the weight of the house. There's supposed to be less settling as a result. I think it simplifies prep too because of this. Less compaction and backfill...
  6. M

    2-Post Lift on Post Tension Slab - Permitting After the Fact

    And that's part of it too. Pulling permits protects that and insurance. Yeah, ground penetrating radar is the method used for mapping out the tension cables. It's typical. Glad we did because the first mounting location I picked was on top of cables. Not good. See pic. So I moved it a few...
  7. M

    2-Post Lift on Post Tension Slab - Permitting After the Fact

    I'm confident everything is up to code electrically. And I've included the electrical part of the lift install in my permit application. But I'm not up to speed on International Residential Code (IRC). So that's what I need to get smart on. But yes, I definitely over think stuff. lol Not over...
  8. M

    2-Post Lift on Post Tension Slab - Permitting After the Fact

    I added 3x 240V branch circuits for mini split, car lift, and air compressor. About to add a sub-panel inside the house with 4x 120V/20A circuits for garage lights, permanent holiday lights, patio lights, and attic lights. Might sound like a lot but one of the 240V circuits was a 50A RV outlet...
  9. M

    2-Post Lift on Post Tension Slab - Permitting After the Fact

    Warning: Can't put the genie back in the bottle. Please be nice. The short version... Bought a new post tensioned slab AZ home in 2023. Immediately contracted ground penetrating radar survey to map cable locations and confirm slab thickness. Then I drilled, anchored, and wired the lift...