Remember to plan out your circuits well and then add an extra one or two just in case. You can't have too many outlets and putting them now will save you later. Get a book of numbers before you start running to keep it all square.
When you are running to the far side of the room use 3/4 or 1"...
We have a roof!!
Also gutters!
We are still waiting on doors, but they are supposed to be delivered Wednesday.
I will be putting up lights and electric this week as well, so I can turn in the scissor lift.
Despite a little hurricane, we managed to get a good chunk of stuff done on the building over the last couple weeks.
Last wall up!
We will hopefully get the roof knocked out over this weekend and start cleaning up a bit. I dunno what kind of lead time we have on the roll up doors yet, but...
Another week down and more work done.
Some help and a telehandler is making fairly quick work of the framing. Hopefully we can keep up the momentum and get more done in the next few days.
Yeah, I've yet to find a building I can't fill up.
We are looking at some rainfall this weekend, but we are hoping it is fairly mild and doesn't slow us down too much.
Another week closer and more work done.
Our dirt guy came and put down another 150 yds for the slab skirt and we put down 1000 sqft of sod behind him.
Then we tested how well the truck fits. :p
We get the building dropped on Thursday and a couple pieces of equipment on Friday and the fun...