Installed the electrical/CAT6 conduits. Purchased the Pella windows.
Acquired three estimates to have a 32’ X 24’ slick 4” slab poured at 4000psi (about 10 yards) The requirements of the estimates needed to include the following; check for final grade (I have a pile of 1/2” stone if any areas need leveling), pumper truck needed, fill the interior of the cinder blocks not already done (3 to 4 yards), All 3 estimates range between $6500 to $6900. WOW! Frankly, I wasn’t expecting that much.



Acquired three estimates to have a 32’ X 24’ slick 4” slab poured at 4000psi (about 10 yards) The requirements of the estimates needed to include the following; check for final grade (I have a pile of 1/2” stone if any areas need leveling), pumper truck needed, fill the interior of the cinder blocks not already done (3 to 4 yards), All 3 estimates range between $6500 to $6900. WOW! Frankly, I wasn’t expecting that much.