October 8-9 -Foam Insulation
Finally time for insulation. This was the final work needed before I could move any stuff in. I decided to go with the company of guy I met at the gym. They sprayed 1 inch of closed cell insulation. They could paint the insulation any color I wanted, but I chose to go with a gray. I felt like white would get dirty quickly, and black didn't really suit the theme I wanted.
The first 8 feet was left unpainted, as I will be covering those parts of the walls with plywood. That cut down the original quoted price a little bit, and I still have an extra bucket of paint should I need it for repairs and touch ups. I highly recommend getting any visible insulation painted, as this stuff doesn't take very long to start yellowing.
The entire process took about 1.5 days, with most of the work accomplished on day one. The second day was just touch-up and clean-up.
Side note: If you have this work done, make sure you mention anything that you don't want removed or cut. One of the workers cut the Ethernet cable that I was running from the house, which was really annoying, but it wasn't too big of a deal to fix. Overall I was very happy with the work.
The prep work. Everything not intended to be covered was masked. That includes light fixtures, outlets, doors, and garage hardware. The wiring was sprayed over, which I recommend for aesthetic purposes and protection.
The Shervin-Williams truck arrived right on time with the paint. I didn't even realize they did deliveries. The insulation company took care of getting the paint.


Starting to spray:


The insulation cured very quickly. Once enough coverage was made with insulation, another crew member began painting while the other continued to spray foam.