jwith68
Well-known member
I'll disappoint some of you right up front, though. Its going to be a "garage" (for farm equipment mainly) so I'm putting it in "Garage Gallery". However, its not going to be a shop. Thought some might like to see how its constructed, and it could be turned into a shop with fairly minimal effort.
Some quick specs:
* 48' x 64' x 14' post frame (pole building)
* Poles 8' OC for walls, Trusses 4' OC
* 18" soffits on all sides
* 1 - 22' double slider centered on a 64' side wall
* 1 - 3-0 walk door
* 6' x 10' porch roof over walk door
* 8' x 48' 50lb/sqft mezzanine on one end of building with stairs
* Scissor trusses from edge of door to end with mezzanine, for extra vertical clearance
* 2x6 interior grade board and 2x4 bookshelf girts (in addition to exterior girts) to 8'-6" above floor
* Interior covered with 7/16" OSB from top of grade board, up 8'
* Double bubble foil insulation over whole building
* Gray 5-rib metal walls, white 5-rib metal roof, white trim
We've had a building pad built up since last October, but it wasn't until about April 8 that it got dry enough to do a final leveling and start drilling holes.
Here's the building site, leveled and ready to start, with first materials delivered.
And on April 15, poles are planted.
Evening of April 21, wall girts and grade boards on, trusses delivered.
April 22, trusses set and braced, ~2/3 of the roof purlins on.
Transition from Scissor trusses to regular trusses.
That's about where it is today, crew will be back tomorrow to finish framing. Should have a decent amount of metal on by the end of the week.
Some quick specs:
* 48' x 64' x 14' post frame (pole building)
* Poles 8' OC for walls, Trusses 4' OC
* 18" soffits on all sides
* 1 - 22' double slider centered on a 64' side wall
* 1 - 3-0 walk door
* 6' x 10' porch roof over walk door
* 8' x 48' 50lb/sqft mezzanine on one end of building with stairs
* Scissor trusses from edge of door to end with mezzanine, for extra vertical clearance
* 2x6 interior grade board and 2x4 bookshelf girts (in addition to exterior girts) to 8'-6" above floor
* Interior covered with 7/16" OSB from top of grade board, up 8'
* Double bubble foil insulation over whole building
* Gray 5-rib metal walls, white 5-rib metal roof, white trim
We've had a building pad built up since last October, but it wasn't until about April 8 that it got dry enough to do a final leveling and start drilling holes.
Here's the building site, leveled and ready to start, with first materials delivered.
And on April 15, poles are planted.
Evening of April 21, wall girts and grade boards on, trusses delivered.
April 22, trusses set and braced, ~2/3 of the roof purlins on.
Transition from Scissor trusses to regular trusses.
That's about where it is today, crew will be back tomorrow to finish framing. Should have a decent amount of metal on by the end of the week.






