twenty8tudor
Active member
- Joined
- Aug 1, 2012
- Messages
- 30
been reading a lot of post on here when i decided to put on an addition to my house. its a 26'x28' with 12' ceiling.
Had a fellow car guy that has a general contracting business do the structure
work and roofing. he is to come back in the spring to do the siding. Also had a buddy help pour the floor.
The inside work I did myself. never doing any major construction before it was a big learning experience. As far as specs are concerned..
i setup the heating system with a water heater in the basement and run the feed and return the 2" conduit with pipe insulation around the pex under an existing room in the house.
insulated the footer and floor along with a plastic vapor barrier. walls are 2x6 studding with a vapor barrier also.
Tried my hand at installing the garage door which is an 18x10 commercial door. Few trial and errors on that part but got the bugs worked out and its operating very well.
i did all the tin work in the inside which was not as hard as i thought it would be. T5 lighting and a 65amp feed from the 200amp box in the basement.
Time to build from start to finish was aboue 2.5months. still have to put a sealer on the floor but heat is on and i can tinker in there as i finish up little things. I will probably be on the board if i run into something i cant figure out.
Thanks for all the info posted on the board!!
started out with this rotten overhang on the house
footers dug and block laid
walls going up
walls closed in and roof on
bringing the insulation home
insulation down and tubing laid
wall up to straighten old crooked brick and block wall
ceiling up
white of the walls started
blue section installed
garage door installed
end wall closed in
tv up, other end wall closed in, new walkin door and garage door frame straightened out
finished till it gets warmer to do the siding
hope ya like it.
Had a fellow car guy that has a general contracting business do the structure
work and roofing. he is to come back in the spring to do the siding. Also had a buddy help pour the floor.
The inside work I did myself. never doing any major construction before it was a big learning experience. As far as specs are concerned..
i setup the heating system with a water heater in the basement and run the feed and return the 2" conduit with pipe insulation around the pex under an existing room in the house.
insulated the footer and floor along with a plastic vapor barrier. walls are 2x6 studding with a vapor barrier also.
Tried my hand at installing the garage door which is an 18x10 commercial door. Few trial and errors on that part but got the bugs worked out and its operating very well.
i did all the tin work in the inside which was not as hard as i thought it would be. T5 lighting and a 65amp feed from the 200amp box in the basement.
Time to build from start to finish was aboue 2.5months. still have to put a sealer on the floor but heat is on and i can tinker in there as i finish up little things. I will probably be on the board if i run into something i cant figure out.
Thanks for all the info posted on the board!!
started out with this rotten overhang on the house
footers dug and block laid
walls going up
walls closed in and roof on
bringing the insulation home
insulation down and tubing laid
wall up to straighten old crooked brick and block wall
ceiling up
white of the walls started
blue section installed
garage door installed
end wall closed in
tv up, other end wall closed in, new walkin door and garage door frame straightened out
finished till it gets warmer to do the siding
hope ya like it.
