Dawgfan77
Member
I would like some opinions from you guys on something I've been kicking around. I'm at the point where I'm about order and install my vapor/radiant/insulation barrier over my pole barn purlins for my roof. I describe it that way because that's what the manufacturer calls it, I realize that's a complicated subject. This is an enclosed concrete floor pole barn garage.
Floor-6-8mil plastic under the slab
Walls and roof- 5-10mm thick closed cell foam faced with foil on both sides
full length ridge vent and vented overhangs
Every pole barn contractor I've talked with installs it the same way-pulled directly across purlins snug to the metal roof. I suspect because this is the quickest/easiest method... not necessarily the best.
On the contrary, the red iron type steel building guys around here install it similar, except with an intentional sag (4-8") in it between the purlins to provide an air gap.
Everything I read about radiant barriers (or insulation) seams to point towards requiring the air gap between them and the roof metal in order to be effective
My question is 2 parts,
1) do you guys agree with the "air-gap" method
2) if so, would it be worth my time to go 1 step further and instead of just a loose sag of the material, actually tack it to the bottom of each purlin as it crosses. Effectively turning the loose arch of insulation into a tight pan with 90 degree angles. I figure a good pile of fairing strips would make it a little less tedious.
I've attached a crude drawing to help describe this a little better. The middle is the typical way its installed around here, the black squares are the purlins(side view) and the red line being the radiant/foil bubble /insulation blanket
Hope the drawing helps. Am I just completely overthinking this? My plan is to start slowly adding rigid foam board to the bottom side of the purlins in the future as budget allows, but honestly that will depend on how bearable the climate is in the shop now. Thanks
Floor-6-8mil plastic under the slab
Walls and roof- 5-10mm thick closed cell foam faced with foil on both sides
full length ridge vent and vented overhangs
Every pole barn contractor I've talked with installs it the same way-pulled directly across purlins snug to the metal roof. I suspect because this is the quickest/easiest method... not necessarily the best.
On the contrary, the red iron type steel building guys around here install it similar, except with an intentional sag (4-8") in it between the purlins to provide an air gap.
Everything I read about radiant barriers (or insulation) seams to point towards requiring the air gap between them and the roof metal in order to be effective
My question is 2 parts,
1) do you guys agree with the "air-gap" method
2) if so, would it be worth my time to go 1 step further and instead of just a loose sag of the material, actually tack it to the bottom of each purlin as it crosses. Effectively turning the loose arch of insulation into a tight pan with 90 degree angles. I figure a good pile of fairing strips would make it a little less tedious.
I've attached a crude drawing to help describe this a little better. The middle is the typical way its installed around here, the black squares are the purlins(side view) and the red line being the radiant/foil bubble /insulation blanket
Hope the drawing helps. Am I just completely overthinking this? My plan is to start slowly adding rigid foam board to the bottom side of the purlins in the future as budget allows, but honestly that will depend on how bearable the climate is in the shop now. Thanks

