Hi guys - I found out about this site from a friend about one week into my build. Awesome place - I have killed many hours on this board already. Now that things are finally slowing down, I have a chance to document my progress.
We were originally looking into putting a detached garage in the back of the property. Two things killed those plans. One was zone restrictions on detached structures and the second was the location of my septic tank. So, after some thought, my wife and I came up with this:
What we have:
What we planned:
Note that the lines in my back yard are the location of my leach lines. Hence final location of garage.
I decided to contract out most of it. I am still doing the siding, all interior finishing, and all of the electric. The original service entrance cable was in the way, so I relocated my meter to the new garage and added a 200 amp main in the garage, which feeds my 100 amp panel in the house. My inspection is this Thursday, and then the power company can come and switch things over to the new service.
As of right now, I have to finish siding the front and one side in the back, and then do all my interior work. Concrete was poured last week. Inside, I have a 10' ceiling for the first 14' and a scissor truss setup for the last 16' that gives me a 12' ceiling.
Well, I'll try to let the pics do the talking...
We were originally looking into putting a detached garage in the back of the property. Two things killed those plans. One was zone restrictions on detached structures and the second was the location of my septic tank. So, after some thought, my wife and I came up with this:
What we have:
What we planned:
Note that the lines in my back yard are the location of my leach lines. Hence final location of garage.
I decided to contract out most of it. I am still doing the siding, all interior finishing, and all of the electric. The original service entrance cable was in the way, so I relocated my meter to the new garage and added a 200 amp main in the garage, which feeds my 100 amp panel in the house. My inspection is this Thursday, and then the power company can come and switch things over to the new service.
As of right now, I have to finish siding the front and one side in the back, and then do all my interior work. Concrete was poured last week. Inside, I have a 10' ceiling for the first 14' and a scissor truss setup for the last 16' that gives me a 12' ceiling.
Well, I'll try to let the pics do the talking...
Last edited: