Dave Carney
Well-known member
Having a 42x48x14' pole barn built, clear span trusses, 6" concrete, 3 overhead doors, overhang, wainscoting, blah blah blah.....So after getting bids from 7 different places, I'm basically down to one contractor. He lists his payment terms as one third in advance, one third after it's framed, one third upon completition. This would be completely contrary to how I've ever done business. I think at the point it's framed, and he has 2/3 of my money, and all I have is poles, no skins, no concrete, the deck is stacked completely against me. This is a small company and I empathize with the cash flow difficulties but what is reasonable...what have you guys done? I can't afford to lose my money.




Tell me about it! The contractor I was referring to in this thread is already out of the picture....never had so much trouble spending so much money....but it all worked out...going to order the building tomorrow morning from another place. $5500 down and a real brick and mortar business...