Need to send power to a shed. About 50ft run. Will either come off meter panel or be a subpanel off shop. shop is only 100 amp, #2 wire though, so looking into a 4 breaker meter panel.
It has a 5hp and 3hp air compressor, 2 oil boilers (figure 10 amps each max, more like 5 running), 10 amp air dryer, couple lights, maybe a hanging water to air heater, couple courtesy outlets
My math is working that 60 amp would be more than plenty? #2 4 wire wire is about $3.25 a foot. #4 is about $1 less