Since I've had work underway for almost a year, I figured I would start my main garage thread.
It's going to be a 24x30 with gambrel trusses which will have an 11x30 room upstairs. I got a set of plans last year from a local supply company and started looking for someone to build it for me.
After several false starts with busy contractors, a friend of mine's cousin said he could put in the frost wall and floor. I had talked to him in the fall, then one day out of the blue in May I got a text he would be out the next day. His company did a great job, and were done in just under a month. Here's a few of his work. He tended to arrive after I went to work and was gone before I got home, so there wasn't any action shots. I do have a ton of photos of the work in progress, but I'll just put the short version here. I'm told he's no longer taking on customers and are just doing their own builds now.







We had a heavy rain just before they finished up which showed a new underground spring coming out near the garage. I got the local excavation guy to put in a french drain above where the garage is going. I also had him do a little finessing on the yard. He was pretty busy and had his 19yo daughter tackle the job. She did a great job.


So this was the state of it last June when I starting trying to line up someone to build it.

It's going to be a 24x30 with gambrel trusses which will have an 11x30 room upstairs. I got a set of plans last year from a local supply company and started looking for someone to build it for me.
After several false starts with busy contractors, a friend of mine's cousin said he could put in the frost wall and floor. I had talked to him in the fall, then one day out of the blue in May I got a text he would be out the next day. His company did a great job, and were done in just under a month. Here's a few of his work. He tended to arrive after I went to work and was gone before I got home, so there wasn't any action shots. I do have a ton of photos of the work in progress, but I'll just put the short version here. I'm told he's no longer taking on customers and are just doing their own builds now.







We had a heavy rain just before they finished up which showed a new underground spring coming out near the garage. I got the local excavation guy to put in a french drain above where the garage is going. I also had him do a little finessing on the yard. He was pretty busy and had his 19yo daughter tackle the job. She did a great job.


So this was the state of it last June when I starting trying to line up someone to build it.