I'm in the middle of construction for a 40x64 pole building (not me, but I'm the GC).
While the plumbers are connecting water/septic, they'll have a trench from garage to my house, where most of the utilities enter. As an IT guy, I'm planning on real connectivity out there, and I've settled on 2xCat6a direct bury runs. I'm planning on sharing the trench with the utilities, and entering both the home and garage.
Direct bury for the main run, and then the vertical along the house/garage would be in Sch80 with what I think is a service elbow going in. Then what?
Looks like 3/4" schedule 80 is big enough for this. OD of the pipe is 1.05" (so 1 1/16 drill). On the house, that's a poured foundation for my basement. Hammer drill @ 1 1/16, then some type of sealant around both the outside and inside of the conduit? What about entering the side of the pole barn? 6x6 w/ 2x4 purlins every 2'). No interior finish yet, but there will be insulation and wall finish. Again, outside the pipe and then inside the pipe (Probably at both ends?).
Basically I'm thinking a 90* setup that goes down the 18-24" to pick up the cables from the trench, then enter each building and then off to the nearby patch panel (cables will be grounded only on one building to prevent a ground loop).
Thanks!!!
-Rick
While the plumbers are connecting water/septic, they'll have a trench from garage to my house, where most of the utilities enter. As an IT guy, I'm planning on real connectivity out there, and I've settled on 2xCat6a direct bury runs. I'm planning on sharing the trench with the utilities, and entering both the home and garage.
Direct bury for the main run, and then the vertical along the house/garage would be in Sch80 with what I think is a service elbow going in. Then what?
Looks like 3/4" schedule 80 is big enough for this. OD of the pipe is 1.05" (so 1 1/16 drill). On the house, that's a poured foundation for my basement. Hammer drill @ 1 1/16, then some type of sealant around both the outside and inside of the conduit? What about entering the side of the pole barn? 6x6 w/ 2x4 purlins every 2'). No interior finish yet, but there will be insulation and wall finish. Again, outside the pipe and then inside the pipe (Probably at both ends?).
Basically I'm thinking a 90* setup that goes down the 18-24" to pick up the cables from the trench, then enter each building and then off to the nearby patch panel (cables will be grounded only on one building to prevent a ground loop).
Thanks!!!
-Rick