bluedog225
Well-known member
There is a long backstory. But the quick version is one of four peers got poured short. Years past. Photos below may help where my explanation falls short.
I spent many hours digging out to the pier so I could expose the top of the concrete column. It’s about 5.5 feet down. I had to dig the hole big enough to allow me to get down in there and scoop out the mud, clay, and sand. It was a fun job. Therefore, it’s not a clean 12” hole.
I want to place a piece of sonotube in the hole and pour the pier up to the level of the soil (and the level of the other 3 piers.
I’ll need to splice a short section of tube to the 4 foot section. I’m hoping will give the new column roughly the same performance characteristics of the other columns.
Is there an accepted way of splicing two pieces of sonotube together? I was thinking of three plywood cleats screwed around the edges on top of duct tape. Alternatively, or in addition, I can put full length two by fours screwed from the inside. And then drop the assembly into the hole and pack dirt on the outside to hold it in place.
Thanks




I spent many hours digging out to the pier so I could expose the top of the concrete column. It’s about 5.5 feet down. I had to dig the hole big enough to allow me to get down in there and scoop out the mud, clay, and sand. It was a fun job. Therefore, it’s not a clean 12” hole.
I want to place a piece of sonotube in the hole and pour the pier up to the level of the soil (and the level of the other 3 piers.
I’ll need to splice a short section of tube to the 4 foot section. I’m hoping will give the new column roughly the same performance characteristics of the other columns.
Is there an accepted way of splicing two pieces of sonotube together? I was thinking of three plywood cleats screwed around the edges on top of duct tape. Alternatively, or in addition, I can put full length two by fours screwed from the inside. And then drop the assembly into the hole and pack dirt on the outside to hold it in place.
Thanks





