I recently put a 100 amp panel in my shop building (new build). The panel will be fed from a 3 wire (2 hot and 1 neutral) lines. The power will run from the service entrance, then to a 200 amp generator transfer switch, then at the transfer switch we will send power to the house (when it's built) as well as routing power to the shop panel.
The neutral and the ground are not bonded together (but there is a screw in the kit to bond them together through the panel case).
My understanding is that since the service entrance is grounded, that the shop panel must also be bonded to the neutral in the panel because there is not a 4th wire carrying the ground back to the service entrance.
I am running a 30 amp circuit (10/3 wire) and a 50 amp circuit (8/3 wire) so all the 220 volt circuits will be wired with a separate ground. Around here, a lot of builders still build with just 2 hot lines and 1 neutral in 220 volt circuits. The price difference between wire with a ground and without a ground isn't much so I'm going with 4 wires for each 220 volt circuits.
Am I right?
The neutral and the ground are not bonded together (but there is a screw in the kit to bond them together through the panel case).
My understanding is that since the service entrance is grounded, that the shop panel must also be bonded to the neutral in the panel because there is not a 4th wire carrying the ground back to the service entrance.
I am running a 30 amp circuit (10/3 wire) and a 50 amp circuit (8/3 wire) so all the 220 volt circuits will be wired with a separate ground. Around here, a lot of builders still build with just 2 hot lines and 1 neutral in 220 volt circuits. The price difference between wire with a ground and without a ground isn't much so I'm going with 4 wires for each 220 volt circuits.
Am I right?