Day 34:
Four framers worked throughout the day. First thing in the morning was raising the east wall into its upright position. Then assembly of north and south walls and lifting of the north.

Most difficult task of the day was lifting the three LVL beams into position. Even with 5 guys and a fine JD 5403 tractor with forks (which I covet … another tractor … I’m afraid that I need some serious professional help) it was a dicey job as those beams were long and heavy. Once the beams were up, the west wall was tied in to the beams and the south wall was raised to standing. Final task of the day was squaring of the east wall in preparation for installation of OSB tomorrow.

Four framers worked throughout the day. First thing in the morning was raising the east wall into its upright position. Then assembly of north and south walls and lifting of the north.

Most difficult task of the day was lifting the three LVL beams into position. Even with 5 guys and a fine JD 5403 tractor with forks (which I covet … another tractor … I’m afraid that I need some serious professional help) it was a dicey job as those beams were long and heavy. Once the beams were up, the west wall was tied in to the beams and the south wall was raised to standing. Final task of the day was squaring of the east wall in preparation for installation of OSB tomorrow.