Sorry for the delay in updating. We've had a lot of rain the last couple of weeks and it’s stopped all progress. We got close to 18" of rain in the Houston area in a short period of time.I have standing water in my yard and that has delayed the delivery of the building. I called the building people yesterday and we are just waiting for the area to dry up, so hopefully they can deliver by the end of the week or early next week. Stay tuned and thanks for the patients.
Rain delay ? man I'd love to have a rain delay.
I'm sure I'll spend a day or two just cleaning the shop once it's complete before I start moving stuff in.



I worked most of the day Saturday cleaning and sweeping. I finally got the shop “dried in” Friday. As with my luck, Mueller ordered the wrong parts so there was a delay in getting everything to finish, also the erection crew got busy and had to work me back into the schedule; so that delayed the finish another two weeks. We’ve had a lot of rain so I haven’t taken any new pictures, maybe tonight if I’m not too busy digging the trench for the electrical.