c6matt
Well-known member
I had the footers dug, and we hit a pipe, hmmm, why is that there? when I bought the house last I was told the septic was in the back. Its on the side, and its dead center of where my 30x48 was going to go. I just spent 2 months getting the size and location past the planning board, and now no matter what I have done I have to have the environmental inspector sign off on it. Ugh, after all the waiting the footings and the floor were to be finished next week, I'm back to square 1.
Crazy idea, could I extend the leech field past the foundation and put a tank access in the floor?
Should I move the garage back?
So frustrated right now...any other ideas?
How it sits today..
Crazy idea, could I extend the leech field past the foundation and put a tank access in the floor?
Should I move the garage back?
So frustrated right now...any other ideas?
How it sits today..