bob_mp
Well-known member
Hi,
I am getting some information from the building department on grounding requirements that I don't understand and want to know if I am missing something.
I have a 400 amp main panel on my detached shop. It has 2 200A main breakers that feed two subpanels, one inside the shop and one inside the house. The house will be connected to the main panel through 3/0 conductors through PVC conduit. I have the main panel connected to the UFER ground in the shop and to a ground rod (next to the service entrance).
Before I upgraded the service (from 200A), I had a continuous #4 conductor that went from the ground connection at the main panel, through the house, to the cold water pipe. I had a separate ground connection (#4) that went from the main panel to the house subpanel.
I was told by the building inspector is that I don't need to connect the grounds between the main panel and the house subpanel and that I needed to connect the ground at the house subpanel to the cold water pipe and a ground rod near the house.
The lack of a ground connection between buildings could result in a difference in potential between the shop ground (and neutral conductor) as compared to the cold water pipe, which doesn't seem right (or desirable).
I am planning on having a phone in the shop which creates a metallic connection between the buildings per NEC 250.32, which (I think) means I need to run a ground wire between the main panel and the house subpanel in any case.
A few questions:
1. Where does the ground connection to the cold water pipe get made? Is it from the subpanel in the house or back to the main panel?
2. Is there a section of the code or other reference that clarifies this?
3. What size conductor is needed? Is it a #4 conductor or do I size it based on Table 250.66, which seems to suggest 1/0 Cu conductor?
Much obliged for the help.
Bob
I am getting some information from the building department on grounding requirements that I don't understand and want to know if I am missing something.
I have a 400 amp main panel on my detached shop. It has 2 200A main breakers that feed two subpanels, one inside the shop and one inside the house. The house will be connected to the main panel through 3/0 conductors through PVC conduit. I have the main panel connected to the UFER ground in the shop and to a ground rod (next to the service entrance).
Before I upgraded the service (from 200A), I had a continuous #4 conductor that went from the ground connection at the main panel, through the house, to the cold water pipe. I had a separate ground connection (#4) that went from the main panel to the house subpanel.
I was told by the building inspector is that I don't need to connect the grounds between the main panel and the house subpanel and that I needed to connect the ground at the house subpanel to the cold water pipe and a ground rod near the house.
The lack of a ground connection between buildings could result in a difference in potential between the shop ground (and neutral conductor) as compared to the cold water pipe, which doesn't seem right (or desirable).
I am planning on having a phone in the shop which creates a metallic connection between the buildings per NEC 250.32, which (I think) means I need to run a ground wire between the main panel and the house subpanel in any case.
A few questions:
1. Where does the ground connection to the cold water pipe get made? Is it from the subpanel in the house or back to the main panel?
2. Is there a section of the code or other reference that clarifies this?
3. What size conductor is needed? Is it a #4 conductor or do I size it based on Table 250.66, which seems to suggest 1/0 Cu conductor?
Much obliged for the help.
Bob