ive got an abundance of #4-4-4 service cable (aluminum) left over from a job.
depending on length and temp, i hear a lot of different amp ratings.
will be powering 8 tube lights, outside security light, a 21A(max) compressor, and at most a miller 210. the welder and compressor will never run at the same time.
is 4 adequate or should i spend a few bucks and run the #2.