Well-known member
Hey guys just poured a 60 x 36 yesterday, the temp down here in Florida right now is mid 50's. We were done pouring around noon yesterday and the guys left around 6 pm. They kept power troweling but the concrete didnt seem to set. When they were leaving you could still touch it and leave a finger print. So one of the guys said he would leave and take his partner home and then swing by again to try and water polish it. He stopped by about 45 min later and it still wasnt right. He is coming by this morning to water polish again and then burn it in. My big question is I know control joints should be cut sooner than later but they say instead of cutting them today we should cut tomm. because if the concrete is wet it will chip when they cut it. Will this be okay? or should I insist on cutting today?