Havent made a build thread yet (but is coming), but im just about done my 40x48x16 pole barn. We were going to do concrete (6") tommorrow and friday, but today my concrete guy calls and says he wants to do my floor in 2 pours, instead of 1 like we had originally talked about.
So, i guess my dilemma is, should I just let him do it in 2 pours, and deal with a joint in the floor, or should I find someone who is willing to do it in one pour? (which may have to wait until spring at this point)
I know there would have to be saw cuts in the single pour slab, but im thinking that they are relatively small compared to a full blown joint?
Any input is appriciated!