Sorry guys. I know this has been beat to death. I did a search and found a boat load of threads but the amount of info was making my pea brain hurt.
Here we go......
North Louisiana. 39 X 55 slab. Vapor barrier planned. Soil won't be compacted properly (An excavator or dozer will be rolled over it) . Got an estimate for 13K for a 6" slab (5K for dirt work) with footers and two 12" beams running the length and three running the width. Rebar and mesh wire throughout. No mention of the PSI rating.
I have a two ton dump truck and a small Kubota excavator that are the heaviest pieces of equipment that will be on the slab.
The 13K price is more than I wanted to pay. So, exactly what do I need at a minimum to be installed here? I do alot of welding on the ground for larger projects so I need it to be as flat as reasonably possible.
Here we go......
North Louisiana. 39 X 55 slab. Vapor barrier planned. Soil won't be compacted properly (An excavator or dozer will be rolled over it) . Got an estimate for 13K for a 6" slab (5K for dirt work) with footers and two 12" beams running the length and three running the width. Rebar and mesh wire throughout. No mention of the PSI rating.
I have a two ton dump truck and a small Kubota excavator that are the heaviest pieces of equipment that will be on the slab.
The 13K price is more than I wanted to pay. So, exactly what do I need at a minimum to be installed here? I do alot of welding on the ground for larger projects so I need it to be as flat as reasonably possible.