This is an older house and currently the garage is fed from a 15A breaker from the main breaker panel with two runs of 14 gauge wire underground. I'm looking to buy a 240v compressor, which requires a wiring upgrade. My thought is to install a 60A subpanel in the garage - 30 amp 240V breaker for compressor and two 15A 120V breakers (lights and then misc. tools). With the mountain of codes and types of materials to use, I have a list of questions.
To start, here's the layout:
1) The run from the garage to the house is ~50 feet if following the concrete patio. Closer to 35-40 feet if ran direct from garage inlet to house entrance. My thought was to use 6/3 cable with a separate 8 gauge bare wire for ground. Any recommendations against or for this?
2) Haven't dug the wire up yet, but expecting a direct bury or 3/4" conduit. This won't be big enough. The plan was to install 1 1/4" pvc conduit buried @ 18 inches. Does this sound correct?
3) What type of wire is allowed for the conduit setup listed above? Seems like I'll be looking for UF cable. Are there other options? The codes/ratings seem to overlap and it's hard to keep track of it all.
4) Per detached building code, 2 grounding rods will be needed next to garage (near inlet) connected to subpanel via 8 gauge bare wire (isolated from neutral bar). Also, these rods need to be buried. Does this sound correct?
To start, here's the layout:
1) The run from the garage to the house is ~50 feet if following the concrete patio. Closer to 35-40 feet if ran direct from garage inlet to house entrance. My thought was to use 6/3 cable with a separate 8 gauge bare wire for ground. Any recommendations against or for this?
2) Haven't dug the wire up yet, but expecting a direct bury or 3/4" conduit. This won't be big enough. The plan was to install 1 1/4" pvc conduit buried @ 18 inches. Does this sound correct?
3) What type of wire is allowed for the conduit setup listed above? Seems like I'll be looking for UF cable. Are there other options? The codes/ratings seem to overlap and it's hard to keep track of it all.
4) Per detached building code, 2 grounding rods will be needed next to garage (near inlet) connected to subpanel via 8 gauge bare wire (isolated from neutral bar). Also, these rods need to be buried. Does this sound correct?
Last edited: