Soon to start pouring the footings and stem walls for the 60'X30' garage project. For every question I get answered here I come up with two new ones. This site is great.
1. Since I am putting radiant heat in the floor... is my assumption correct that the insulation between the stem wall and Floor will also serve as a perimeter expansion joint?
2. What about the perimeter slab area where the overhead doors close? Do you insulate vertically along the slab in this location as well (between slab and drive way approach)? If so, Do you seal this joint?
3. I have read dozens of threads concerning expansion joints or saw cuts in the slab itself and still confused. I plan on finishing the floor with epoxies and can't seem to find a consensus what is best. Any advise?
1. Since I am putting radiant heat in the floor... is my assumption correct that the insulation between the stem wall and Floor will also serve as a perimeter expansion joint?
2. What about the perimeter slab area where the overhead doors close? Do you insulate vertically along the slab in this location as well (between slab and drive way approach)? If so, Do you seal this joint?
3. I have read dozens of threads concerning expansion joints or saw cuts in the slab itself and still confused. I plan on finishing the floor with epoxies and can't seem to find a consensus what is best. Any advise?