To avoid these ads, REGISTER NOW!

Cost breakdown and lessons learned on newly built 35x50x16

jetranger

Well-known member
Joined
Jul 18, 2014
Messages
129
Location
USA
Just finishing up my 35x50x16 and I wanted to share some information, including a cost breakdown and a few lessons learned throughout the process.

Location - Las Vegas, NV
Stick build
Stucco siding
Asphalt shingle roof
Overhead doors: 14x14, 12x12, 12x12
My wife and I did pretty much everything... and a few friends would help sometimes along they way. Only things we hired out was concrete and stucco!

First of all - costs. I'm posting these because I feel like it's extremely hard to get accurate price estimates on stick built shops... mostly because if it's your first project of this type you really won't know what's needed till you've already paid your engineer to make your plans.

Soil sample (req'd by city, tells engineer how thick slab needs to be) - $1,400
City building permits - $1,700
Architectural plans - $0 (given to me by a neighbor that had a similar shop built)
Structural Engineer - $1,000
Concrete slab (5", 4500psi, pad prep, finishing) - $15,750
Lumber (2x6's, OSB for roof and walls, garage door beams) $7,000
Trusses - $3,400
Hardi Frames (req'd by engineer for sheer on front wall) - $1,700
Overhead doors (insulated, sectional) - $5,400
36" man door - $200
Stucco (3 coat) - $8,600
Asphalt shingles and roofing supplies - $2400
Paint (20 gallons req'd) - $600

Total - $49,150 for an empty shell of a shop including no wiring, lighting, insulation, drywall

Pad poured -
20200208_091912.jpg


Cool drone night shot -
20200324_200147.jpg


Setting the last truss -
20200313_155019.jpg


Installing OSB -
20200409_112440.jpg


OSB on and doors in -
20200419_160546.jpg


Stucco scaffolding up and getting ready to shingle -
20200428_133958.jpg


Stucco done and roof done -
20200503_185803.jpg


Painted and complete exterior -
dusk.jpg



Moving on to the lessons learned -

1. During construction, I wished I had put a 3rd overhead door on the adjacent wall for a few reasons. First was airflow. With the OSB on there was absolutely 0 airflow, even with both doors open. I can't even describe how much having that extra opening helps with airflow and lower temps. Second, in the summer evenings with the sun low, it would shine directly into the shop. I wanted to be able to have an overhead door open at all times throughout the day for natural light, but without the sunshine directly coming in. Third, access. Being able to pull in another vehicle without moving 2 or 3 others is a huge convenience. I knew I wouldn't be happy until the 3rd door was in, so I made it happen. It would have been easier and cheaper to do it from the beginning obviously, but overall it wasn't bad.

2. With most construction, there are delays and unforeseen costs which I expected. Although, the stucco took about 2 months total. I really thought it would take closer to 3 weeks. I chose 3 coat for the durability over 1 coat, but between setting up scaffolding, lath, and all 3 coats, the stucco took A LOT longer than expected, and with the scaffolding set up I was unable to use the overhead doors.

4. I ended up having to use the Hardi-Frames on the front wall since the doors were so large relative to the surface area of the wall. I did not know I needed these prior to engineering, but at that point I had already paid. What I found out later from a co-worker that used to frame - had I gone a little wider with the shop I probably wouldn't have needed those frames. He said if you can fit a 4x8 sheet of plywood on the sides/between the doors, that is sufficient for sheer. The Hardi Frames were around $1,700, so it could have been a toss up between the cost of extra material to make the whole shop a few feet wider.

5. Buy as much equipment as you can rather than renting. This might be obvious, but not only does it end up saving money, it takes the stress out of needing to hurry since you know a rental is costing you every day. I ended up buying a scissor lift and forklift which were life savers. The scissor lift was $500, and the forklift was $300. I had to put a little bit of work into each, but it was well worth it!

Here they are -
20200222_072600.jpg


Even if you but a $4,000 forklift and sell it 3 months later for $3,800, that's still better and easier than renting any paying a daily rate.

6. Always try to be present when contractors or inspectors are there. There were a lot of potential problems avoided because I happened to be on-site.

7. I know stucco isn't common for most shop builds here, but having the scaffolding set up was such a huge help for roofing, painting, etc. I asked the stucco guys to leave the scaffolding set up an extra week when they were done to help with paint and they had no problem with that.

8. But a lot of extra 2x4x16's for bracing. Even though there isn't a lot of surface area with framed up walls and with no plywood, they still wanted to move a lot in the wind. Have plenty of extra bracing and ratchet straps!!
 
To avoid these ads, REGISTER NOW!

Metallitubby

Well-known member
Joined
Aug 12, 2019
Messages
25,980
Location
ATL OTP North
Great looking build. I seems like you had a vision initially and tried to stay with that as much as possible. It turned out really nice, simple, and clean looking. Now to finish it with all the goodies!

It looks like you are south by 11 and 215 or so. Sorry if it seems like I'm snooping, but my father lives in Summerlin South. I love Las Vegas for all the outdoor stuff to do.
 
Last edited:

gfd_703

Well-known member
Joined
Apr 22, 2010
Messages
283
Location
west tennessee
Looks great. I am in the finishing stages of my 30x 50 x14 and the numbers sure are different here in TN. Just want to give the other side of building cost
Soil sample (req'd by city, tells engineer how thick slab needs to be) - $1,400
Not required here so $0
City building permits - $1,700
Not required out here in the country $0
Architectural plans - $0 (given to me by a neighbor that had a similar shop built)
Not required $0
Structural Engineer - $1,000
Not required $0
Concrete slab (5", 4500psi, pad prep, finishing) - $15,750
4" with footings, 5000psi , fiber and rebar $6500 finished
Lumber (2x6's, OSB for roof and walls, garage door beams) $7,000
Complete materials package including lumber 2x6 walls and exterior metal $15,000
Trusses - $3,400
Included in package above
Hardi Frames (req'd by engineer for sheer on front wall) - $1,700
Not required
Overhead doors (insulated, sectional) - $5,400
Included in materials package but looks like the one 18x12 insulated was $2125
36" man door - $200
Included in materials package
Stucco (3 coat) - $8,600
I used metal and was included in package
Asphalt shingles and roofing supplies - $2400
Again I used Metal and was included in package
Paint (20 gallons req'd) - $600
No paint required
I also have a 24x20 lean to included in the build, 2X6 framed walls. I also paid for the erection of the building $5800. An expense you avoided by building yourself.
Total - $49,150 for an empty shell of a shop including no wiring, lighting, insulation, drywall
My total for empty shell with lean to, I am doing the electrical but material figured in cost including lights, Electric company will hook up eectrical for free but I did have to pay for inspections $110, 4 loads of gravel and 3 loads of red sand, radiant barrior on alll walls and roof areas, and power opener on over head door. Best I can figure right now I am going to have under $30,000 in the building. As far as not being engineered, the company that built it does about 300 of these type buildings a year so they have it figured out. I did alll sight prep and finish grading myself. Wife has already finished landscaping even before the overhead door is installed or electricity turned on. I hope you enjoy yours as much as I hope to enjoy mine.
 
To avoid these ads, REGISTER NOW!

DJF3

Well-known member
Joined
Feb 15, 2020
Messages
186
Location
British Columbia, Canada
Thanks for both of those cost breakdowns! I'm starting a very similar build. 34x60x16. Here are some costs I know of right now. Keep in mind this is Canada.
Architect $1200
Engineer $750
Lift of 2x6x20 MSR 2100 $3000
Trusses and metal roof $5000 (only half the cost as I'm reusing old trusses and roofing)
Raw concrete cost $15000
2 12x14 overhead doors with openers $9000
Anchors spec'd by engineering $2000
Slab insulation $2600
Fiberglass wall installation $2500
Lighting $2500
No cost yet on electrical, heating, floor finish, hoist, the list goes on and on and on
 

OKDart

Well-known member
Joined
Jun 12, 2012
Messages
84
Location
Oklahoma
On renting equipment....look at monthly rates vs weekly or daily rates. Much better cost and way less pressure. Buying and reselling equipment is widely variable based on unit, condition, location and time of year.

I've been looking for a reasonably priced scissor lift around here for a long time. Dealers buy them all up and then ask too much for them. I've bid on a lot of the ones on local bidadoo eBay listings, and I'm always outbid by one bid at auction close. I'm convinced they're willing to overpay by quite a bit just to make sure no one else gets them.
A co-worker told me about his old boss in the restaurant business that went to all the auctions and bought up restaurant equipment he didn't need just so new restaurant owners had to buy new, hoping to hurt their budget so they would fail. He put all the equipment in storage and never used it.
 

MushCreek

Well-known member
Joined
Jan 14, 2015
Messages
9,818
Location
Upstate South Carolina
Great write-up, and a beautiful shop!

It just goes to show the regional differences, though. Of your first four line items totaling $4100, mine was just $80 for a permit.
 
To avoid these ads, REGISTER NOW!
Top Bottom