I have a 3-car garage with a deep 1-car side and a regular 2 car side connected. I already have installed my 100 amp subpanel next to the main hosue panel and run and pulled a 3/4" EMT conduit with #12 THHN around the entire garage for receptacles. The green loop is fed and protected by a 20 amp GFCI/AFCI breaker. My concern is the end of the run is over 100', especially with elevation changes. I already have a bunch of excess #12, how bad of an idea would it be to run another 3/4" conduit to join both dead end receptacles together with #12? Any issues? I just want to provide a second alternate path for the long leg to reduce voltage drop.
Yes, I could've just run #10, but I have a lot of #12 so it's a sunk cost. I didn't really think a lot about drop when I started. It's not a concern for my 240V runs.