First quote came back at an eye watering $98,000! I think this is a combo go-away number and a factor of us living in a pretty "ritzy" area outside of Pittsburgh where people might spend that kind of $. Copied the quote below.
I think one small part of the problem is I picked a 50x50 area to clear, which on the slope makes for some difficulty. I'm going to spec a rectangular area moving forward.
=====
Access Road and Garage Pad $98,987.63
Includes:
· Mobilization:
o Transport Case 145X Excavator to job site.
o Transport Cat D4C Dozer to job site.
o Transport Bobcat E55 Excavator to job site.
o Transport Bobcat T770 Track Loader to job site.
o Transport Case Off Road Compactor to job site.
· E&S Controls
o Install silt fence as needed down slope of project area as noted in design.
· Land Clearing
o Clear all trees needed to complete project scope in road, building pad, and all cross slopes. Logs to be cut
in 10’ lengths and stored on site, tree tops to be chipped as needed, stumps to be exported offsite.
· Excavating & Grading
o Existing landscaping near driveway to be removed as needed, all material to be kept on site, existing
sidewalk to be removed to existing bend in sidewalk as shown in design.
o Topsoil to be stripped as needed in driveway and building pad areas, topsoil to be stock piled on site.
o Access road to be installed as shown in detail on attached design, road not to exceed 200’ long by 15’
wide. Runoff ditch to be installed on high side of road with 2 culvert pipe crossings, ditch to be lined with
R4 Rip Rap. Access road to be cut to subgrade, install 8oz felt road fabric, install and compact 6” of #3
limestone, install and compact 2” of 2A Modified Limestone. All up slopes and bottom slopes not to
exceed 2:1 grade, all slopes to be final graded with onsite topsoil.
o Building pad to be cut to allow 50’ x 50’ building pad. Cut to not exceed 8’ with a fill side of 4’ in building
pad area. Keyway to be excavated in location of fill area, all fill to be compacted in lifts with equipment on
site. Building pad to be cut to subgrade, install 8oz felt road fabric, install and compact 6” of #3 limestone.
All up slopes and bottom slopes not to exceed 2:1 grade, all slopes to be final graded with onsite topsoil.
· Reclamation
o All final graded areas to be seeded with Contractor Mix Rye Grass Seed.
o All seeded areas to be fertilized with starter fertilizer.
o All planted areas to have straw matting installed and pinned.
· Demobilization
o Transport Case 145X Excavator to job site.
o Transport Cat D4C Dozer to job site.
o Transport Bobcat E55 Excavator to job site.
o Transport Bobcat T770 Track Loader to job site.
o Transport Case Off Road Compactor to job site.