Just bought some property that has 3 different power supplies on it.
House. (110+220)
MIL House. (110)
Shop (110+220) + Grain facility (480).
The Grain facility has it's own 3 phase that will likely never be used again. It's pretty much the same distance from the Grain facility to the power pole as it is from the shop to the power pole.
Aside from Electrifying myself (I'm ok with electrical work), how difficult would it be to move the existing 3phase panel from it's existing location into my pre-existing shop? If I reposition it I think I can do it without even changing any cable lengths.
House. (110+220)
MIL House. (110)
Shop (110+220) + Grain facility (480).
The Grain facility has it's own 3 phase that will likely never be used again. It's pretty much the same distance from the Grain facility to the power pole as it is from the shop to the power pole.
Aside from Electrifying myself (I'm ok with electrical work), how difficult would it be to move the existing 3phase panel from it's existing location into my pre-existing shop? If I reposition it I think I can do it without even changing any cable lengths.