Recent content by hoppsxc140

  1. H

    Pole shed vs stick built? Need some help!

    Lots of other variables to consider than just framing materials. Is the builders quote a turnkey package? (Permits,taxes,cleanup,site plan, etc). As previously stated the excavation can also be an area driving up the price. Cut or fill amounts, gravel under the slab, off haul/disposal fees. I...
  2. H

    Work Boots vs Hiking Boots On Concrete All Day

    I work for a paving/material supply company so some days I’ll walk 10 miles on a grind and pave or chip seal job, others I might spend all day in the quarry. I’ve been wearing Whites since 2006 and recently bought my first pair of Nicks. If you can swing the cost, a custom boot is the way to...
  3. H

    $1500 to seal coat asphalt driveway?

    Porous asphalt is designed for water to flow through. Any typical DOT or commercial mix is intended to be impervious and lives the longest being protected. No one is out promoting drilling through driveways or parking lots to “get the flow through back” Sealing is used all over the country...
  4. H

    What did you pay for your slab?

    Yes 50*27=1350/30=45/60= .75’
  5. H

    How do you determine your costs?

    Get as many quotes as possible, I when I built my 36x60 pole building I called 5 builders. 3 took plans and 2 returned prices, one was 25G and change the other was 58. I called the 58 to make sure he understood I only wanted the shell and 2 man doors and he confirmed. Signed with the low guy the...
  6. H

    pour post first then slab?....or all at once....Monolithic including posts

    All of our posts are in concrete. I wouldn’t trust a contractor to do a good enough job compacting with native materials. Think of the utility crossings in a paved road, the bump isn’t from the patch job, it’s from poor compaction underneath and settling over time.
  7. H

    Dirt work 40x60 Pole Building

    Correct, the building height is based off of the high side. So the OP could push all the fill off the building pad and the 18" is still there. 12ft sidewall + 36" depth + 18" of grade means that corner always required at minimum a 16.5ft post.
  8. H

    Dirt work 40x60 Pole Building

    They always had to be longer. Regardless if the fill was placed before the post or after.
  9. H

    Dirt work 40x60 Pole Building

    I could understand a charge for additional concrete if the site condition changed after the quote was issued, but that is a small cost. I didn't see a height listed but if it was going to be 12 ft sidewalls it would be 12 ft from the highest point with the gap Pig9r described above. If not there...
  10. H

    pole building - Gravel size

    Skip the air tamper and use a gas or diesel powered jumping jack from the same rental place.
  11. H

    Best way to keep pipe from freezing

    Heat tape and a spigot cover on the outside. http://www.homedepot.com/p/Hard-Faucet-Cover-1981/204759083
  12. H

    Central Washington 36x60x12

    I wanted to share my build since I've gathered many ideas from everyone else. First a little back story. I purchased a 4 bedroom, 2 bath 1700 sq ft, 2002 manufactured home on 2 acres in 2006, It was a foreclosure and I paid 96,000. At the dead end of a gravel road and surrounded by the back of...
  13. H

    An engineering problem

    Depth is irrelevant when it comes to confined space. https://www.osha.gov/pls/oshaweb/owadisp.show_document?p_table=standards&p_id=9797
  14. H

    An engineering problem

    Here is another option, especially if driving into it is extremely unlikely. http://www.incord.com/baynets/truck-service-bay-covers.htm
  15. H

    An engineering problem

    I can't dig up this invoice but they were right under $6,000.00 for 11 units. 3 of these were standard items. The cost in all of these included the 1ft precast concrete section, engineering and construction on the 8 non standard sizes. The company that sold me the structures doesn't manufacture...
Top Bottom