    Installing a Reznor UDAP250

    I think I am going to hang from the purlin after backing the purlin with a 5' length of uni-strut. Four all threads down to an "H" uni-strut assembly and then a section of threaded to the unit.
  3. T

    Installing a Reznor UDAP250

    I am not considering seismic activity. I will use flexible connections for electrical and LPG
  4. T

    Installing a Reznor UDAP250

    Thanks for the photo. Nice install. I can definitely use threaded rod like yours. I would need to add couplers to extend the length. I would probably do a length to a horizontal unistrut, then rod to the next level.
  5. T

    Installing a Reznor UDAP250

    I bought a used Reznor UDAP250 and I am getting ready to install it. My building is a red iron 40x60x18. I am trying to figure out how to hang it and where. Corners or endwall? Obviously, I have a long drop from the roof to mount at 14-16 feet. Cantilever off the girts? Suspend from the purlins...
  6. T

    New Service help

    Do you have a model number of the meter base
  7. T

    New Service help

    Corrected
  8. T

    New Service help

    I think that relocating the meter probably makes the most 'cents'. Just not sure the paneling requirement to run 100 amps to the shop and 200 to the house. The utility is relocating the meter and the wiring to the house will now go from the transformer to the new panel and back to the house, The...
  9. T

    New Service help

    Not sure why the house location is important but it is 100 feet away, 300 from the shop. By penetration I am talking one conduit hole running a panel inside versus an outside panel requiring multiple conduits to the various circuits. Conduit sweep out of the ground into a LB and then into the...
  10. T

    New Service help

    I have a new shop and now for the electrical. I have two choices for the service. 1 The utility company will relocate my house meter to a location close to the transformer. I will have a meter there and then a circuit to the house and one to the shop 2 A new service with the meter near the...
  11. T

    New install Modine PA150AB

    I am pretty sure your right but could I put an elbow, exit and then vertical for 4 feet? Just don't want to penetrate the roof
  12. T

    New install Modine PA150AB

    I have a chance to buy a used Modine PA150AB but I want to mount it using a horizontal vent line, Is this possible? I realize that type 3 pipe is needed
  13. T

    New service for shop - Code question

    It will be inspected (California). If they want I can always change the breaker
  14. T

    New service for shop - Code question

    I have foundation ground tied to the rebar in the shop, so I am all set there. A main panel in the shop. Remove the neutral bonding screw. So the meter panel with disconnect breaker, 2 ground rods, cable to panel in shop. Thanks for all the. help. Can't wait to get off the generator and...
  15. T

    New service for shop - Code question

    OK. So do the panel with the breaker, 2-2-2-4 AL MHF to the shop and through the wall (conduit) , into the panel? I am familiar with Nassua and will be getting it there. I just wish they didn't immediately call and email when you visit their site