Hello.
My attached garage has 15A plugs, and one 30A for a construction heater.
Garage is used to park cars, snowblower, etc. no welding, woodworking. Mainly car washing, and the odd brake job or minor maintenance stuff. (Brakes never need replacing in July, always January -40 thus the construction heater. )
I have a new power washer that requires a 20A circuit, so what would you do?
1. Replace existing 10g wire with a 6g and instal subpanel
2. Just run a new 20A circuit on some 12g
3. Instal 30A sub panel with existing 10g
Option 1 makes most sense, but overkill for what I need, although cost would be offset by shorter 20A circuit run.
Option 2 is really what I need.
Not sure if option 3 is code or not. I’d just have to connect the neutral. Construction heater and power washer would never be used at the same time.
It’s looking like option 1 or 2. Option 3 was simply because the wire is there
My attached garage has 15A plugs, and one 30A for a construction heater.
Garage is used to park cars, snowblower, etc. no welding, woodworking. Mainly car washing, and the odd brake job or minor maintenance stuff. (Brakes never need replacing in July, always January -40 thus the construction heater. )
I have a new power washer that requires a 20A circuit, so what would you do?
1. Replace existing 10g wire with a 6g and instal subpanel
2. Just run a new 20A circuit on some 12g
3. Instal 30A sub panel with existing 10g
Option 1 makes most sense, but overkill for what I need, although cost would be offset by shorter 20A circuit run.
Option 2 is really what I need.
Not sure if option 3 is code or not. I’d just have to connect the neutral. Construction heater and power washer would never be used at the same time.
It’s looking like option 1 or 2. Option 3 was simply because the wire is there