Looks like a nice start. Floor heat too. What is your plan?
Just a quick description of what will be happening:
Yes, going with radiant and I have a boiler setup which is going to be a closed system with a Axiom feeder tank. (no water source). 5 loops in 1 zone .
Electrical/Wiring: will include exhaust fan for painting - 15 amp, 220V for welder, plasma cutter, pot lights on exterior mounted in sofit area, 220 V wiring for lift motor, boiler wiring. Standard electrical outlets and 8 fluorescant lights.
Gas: Getting gas line run to garage for boiler.
Framing : Doing the framing myself with a friend so hopefully have the major part of this stage completed in 2 weeks. With the interior 12 ft ceiling I was still able to put in a loft for storage. Access to attic will be either by motorized lift or drop down attic ladder.
Interior Layout:
On the right side of garage will be my 4 post lift. Not required to bolt down lift, so no chances of peircing a radiant line.
Left side will be daily driver parking. I have two 10ft wide x 9 ft high doors going in with the liftmaster system (high tracking) . Ceiling heights will be 12ft, and also thinking of doing the bulkhead(overhead storage) like hitByThunder's 24x24 Palace thread.
Work benches , tools, vises , tool cabinets will all be situated at the far wall where the radiant tube come up.
More to come:::