Greetings all,
I have gleaned so much valuable information from the garage journal over the years. Now, finally, I have a project to post about with questions.
We initially used a skid steer to regrade the clay base which was approximately 16 in different from front to back on the long side. We insulated the perimeter with 5 and 1/2 in eps slabs of foam from a salvage concrete dock. Our contractor brought in the gravel and spread it 4 in thick. Now we are cutting 7 in slabs and laying them staggered in a brick pattern on the entire floor. We intend to spray foam the gaps, lay two layers of 6 mil poly, 2-in metal chairs, wire mesh and then affix the PEX to that.
I have the following questions for these steps still to do.
1. Is there some other way of sealing the gaps besides spray foam?
2. What's the best tape to use for the plastic and should it be sealed to the foam perimeter edges?
3. Is there a free or cheap software that will allow me to design the tubing layout
Thank you, Bridgette
I have gleaned so much valuable information from the garage journal over the years. Now, finally, I have a project to post about with questions.
We initially used a skid steer to regrade the clay base which was approximately 16 in different from front to back on the long side. We insulated the perimeter with 5 and 1/2 in eps slabs of foam from a salvage concrete dock. Our contractor brought in the gravel and spread it 4 in thick. Now we are cutting 7 in slabs and laying them staggered in a brick pattern on the entire floor. We intend to spray foam the gaps, lay two layers of 6 mil poly, 2-in metal chairs, wire mesh and then affix the PEX to that.
I have the following questions for these steps still to do.
1. Is there some other way of sealing the gaps besides spray foam?
2. What's the best tape to use for the plastic and should it be sealed to the foam perimeter edges?
3. Is there a free or cheap software that will allow me to design the tubing layout
Thank you, Bridgette