The siding crew showed up this morning and said they would be finished today and that's good news. All that is left on the drywall is the finish sanding and that team also arrived this morning.
Next, I expect the trim carpenters will install the stair stringers, risers and replace the temp treads with finished ones. They will also install 3/4" quarter round at the bottom of the drywall where it is raised slightly off the treated stem wall bottom plate. J channel was specified there to protect the bottom of the drywall but was not done so the quarter round will suffice. Actually, caulked to the drywall and plate, it should be better.
If the drywall guys finish today, the GC will be ready to install the garage doors. Also need to pour the front apron sometime soon. Dominion power has not run power to the garage yet so we are still running extension cords from the house and can't fire up the heat pump until that is done.
Also remaining is prime painting the drywall, running the underground roof drains and finish electric including mounting the ceiling lights and fan. I will be doing the final wall painting, floor coating, interior window/door trim, fluorescent tube installation, compressor installation and piping and bench/cabinet installation so I am very anxious to have the GC done and off the job and free to do my thing. Things are further complicated because spring is here and almost time to de-winterize the boat, open and clean the pool, get the solar heater working, plant flowers, mulch the beds, reseed the lawn, power wash the house and clean up the grounds, all in time to have everything ready, including the garage, for our annual Memorial Day weekend family reunion. The next two months are going to be very busy.
My next post should have photos of the finished siding including shutters which will really dress up the exterior.
Glen
Next, I expect the trim carpenters will install the stair stringers, risers and replace the temp treads with finished ones. They will also install 3/4" quarter round at the bottom of the drywall where it is raised slightly off the treated stem wall bottom plate. J channel was specified there to protect the bottom of the drywall but was not done so the quarter round will suffice. Actually, caulked to the drywall and plate, it should be better.
If the drywall guys finish today, the GC will be ready to install the garage doors. Also need to pour the front apron sometime soon. Dominion power has not run power to the garage yet so we are still running extension cords from the house and can't fire up the heat pump until that is done.
Also remaining is prime painting the drywall, running the underground roof drains and finish electric including mounting the ceiling lights and fan. I will be doing the final wall painting, floor coating, interior window/door trim, fluorescent tube installation, compressor installation and piping and bench/cabinet installation so I am very anxious to have the GC done and off the job and free to do my thing. Things are further complicated because spring is here and almost time to de-winterize the boat, open and clean the pool, get the solar heater working, plant flowers, mulch the beds, reseed the lawn, power wash the house and clean up the grounds, all in time to have everything ready, including the garage, for our annual Memorial Day weekend family reunion. The next two months are going to be very busy.
My next post should have photos of the finished siding including shutters which will really dress up the exterior.
Glen