I’ve been looking to do this for some time, as for the first time in 20 years, I have not had a garage when I bought my home 3+ years ago. What sold me on the house, was not so much the house, but the land. The drawbacks to the house were: end of a dirt road, NO GARAGE and a little further out than I wanted to have for my commute. 2 of the 3 items really have not been a problem and quite easy to ‘accept’. The garage? That one is being solved.... right.... NOW!!!
I actually started prepping for the garage the first week of owning the home. That entailed, clearing a ton of trees and enjoying numerous bonfires and plenty of liver lubricating beverages - aka... beer. Prepping, life, schedules and funds have played into delay after delay. Fast forward to a few weeks ago, and the process has begun. Build permit approved and things are now moving!
Much of the garage I will be doing myself, but I do know my limits and will, and have, hired some of the work out.
I hired the digging of the foundation and the forming/filling of the footing and frost walls. I’ll also be hiring out the setting of the trusses, since at 30’ of span and 2x10 joists - I am thinking they will be a bit unwieldy for a single guy to handle.
Other tidbits:
Went with Insulated Concrete Forms (ICF)
Will have half bath
Closed radiant floor system atop 4” foam board made of the same material as the ICF
I am currently digging a ~275’ trench from the power pole at the road to the right front corner of the garage.
More pics to come!
Look forward to hearing input/suggestions!
I actually started prepping for the garage the first week of owning the home. That entailed, clearing a ton of trees and enjoying numerous bonfires and plenty of liver lubricating beverages - aka... beer. Prepping, life, schedules and funds have played into delay after delay. Fast forward to a few weeks ago, and the process has begun. Build permit approved and things are now moving!
Much of the garage I will be doing myself, but I do know my limits and will, and have, hired some of the work out.
I hired the digging of the foundation and the forming/filling of the footing and frost walls. I’ll also be hiring out the setting of the trusses, since at 30’ of span and 2x10 joists - I am thinking they will be a bit unwieldy for a single guy to handle.
Other tidbits:
Went with Insulated Concrete Forms (ICF)
Will have half bath
Closed radiant floor system atop 4” foam board made of the same material as the ICF
I am currently digging a ~275’ trench from the power pole at the road to the right front corner of the garage.
More pics to come!