So I just had a 1000 sq. ft. monopour slab done for a red iron shop building. The building fabricator highly recommended a concrete contractor who could do the pour and finishing. Had done over 50 slabs for them, been in business for 15 years. I did the excavation, prep and forms. 4" of graded and compacted 3/4 clean stone, 2" of 20psi XPS, 15 mil vapor barrier, forms set within 1/8" in elevation with a laser. #4 rebar, 18" OC and 2 bars top and bottom in the footing. Even did CNC'd plywood bolt carriers to make sure the anchor bolts were dead on. The building inspector said it was the most meticulous slab prep he's ever seen.
I met with the concrete contractor and walked the site and checked my prep. He was a bit rough around the edges but a lot of concrete guys are and he assured me that everything looked good and they'd use a laser during screeding it. I emphasised that I needed a high level of flatness for rolling carts, CNC machine etc. Well, despite having a laser setup during the pour I ended up with a slab that has a 1/2" crown in the center (13 ft. from the edge) and has a lot of closely spaced waves and lumps. I understand that slabs aren't going to be ever dead flat but this is a mess. The saw cut guy who came out later even said it didn't look good. The trowel finish is pretty good and tight but the flatness is terrible. On top of it they left a bunch of rough concrete under the bolt carriers I had to chip and grind off with a cup wheel.
I'm considering getting a scarifier and a grinder/polisher to try and even things up after the building is framed. Is that just crazy or should I work on my zen acceptance? I paid the concrete and pump separately so the only refund I could ask for would be from the finisher. I definitely let the building fabricator know that they shouldn't be recommending this guy.
Photo is pretty typical all over the slab so that's a 3/8" dip in only 3 ft using a 9 ft. track saw track as a straight edge.
I met with the concrete contractor and walked the site and checked my prep. He was a bit rough around the edges but a lot of concrete guys are and he assured me that everything looked good and they'd use a laser during screeding it. I emphasised that I needed a high level of flatness for rolling carts, CNC machine etc. Well, despite having a laser setup during the pour I ended up with a slab that has a 1/2" crown in the center (13 ft. from the edge) and has a lot of closely spaced waves and lumps. I understand that slabs aren't going to be ever dead flat but this is a mess. The saw cut guy who came out later even said it didn't look good. The trowel finish is pretty good and tight but the flatness is terrible. On top of it they left a bunch of rough concrete under the bolt carriers I had to chip and grind off with a cup wheel.
I'm considering getting a scarifier and a grinder/polisher to try and even things up after the building is framed. Is that just crazy or should I work on my zen acceptance? I paid the concrete and pump separately so the only refund I could ask for would be from the finisher. I definitely let the building fabricator know that they shouldn't be recommending this guy.
Photo is pretty typical all over the slab so that's a 3/8" dip in only 3 ft using a 9 ft. track saw track as a straight edge.