Did a search but couldn't locate the an answer to my specific question.
So I got my MaxJax about a year and a half ago and I was using it diligently. But because my garage is rather shallow I didn't have much choice where to locate it. I had to locate it near the relief cuts made in the slab. I knew it was a gamble and it bit my ***. The slab cracked where the anchors were and a few of the anchors would no longer hold torque! Yikes!
So I had a section of the slab cut, dug, and re-poured. I now have a large 3' x 13' x 12" footing that is keyed under the slab with rebar. I only have a picture of the initial cut and dig.
The concrete was poured on November 27th. I know it is recommended that I wait at least 28 days before using a lift, but I thought I could at lease drill the holes and set the anchors for the MaxJax.
Here's my main question.
I bought a fresh set of Wej-it anchors. What's the best way to ensure the anchors bite and set in the new concrete? I had a couple that did not set last time and had to punch them through and install epoxy anchors ($$$). With the footing/base now 12" deep, I cannot punch them through if I have a problem, so I need to make sure they set right the first time.
One thought I had was to use some epoxy on the wejit anchors themselves when setting them. Then wait a day or two and check to make sure they hold 90ftlbs of torque.
Other suggestions or opinions?
Thanks in advance.
So I got my MaxJax about a year and a half ago and I was using it diligently. But because my garage is rather shallow I didn't have much choice where to locate it. I had to locate it near the relief cuts made in the slab. I knew it was a gamble and it bit my ***. The slab cracked where the anchors were and a few of the anchors would no longer hold torque! Yikes!
So I had a section of the slab cut, dug, and re-poured. I now have a large 3' x 13' x 12" footing that is keyed under the slab with rebar. I only have a picture of the initial cut and dig.
The concrete was poured on November 27th. I know it is recommended that I wait at least 28 days before using a lift, but I thought I could at lease drill the holes and set the anchors for the MaxJax.
Here's my main question.
I bought a fresh set of Wej-it anchors. What's the best way to ensure the anchors bite and set in the new concrete? I had a couple that did not set last time and had to punch them through and install epoxy anchors ($$$). With the footing/base now 12" deep, I cannot punch them through if I have a problem, so I need to make sure they set right the first time.
One thought I had was to use some epoxy on the wejit anchors themselves when setting them. Then wait a day or two and check to make sure they hold 90ftlbs of torque.
Other suggestions or opinions?
Thanks in advance.

