I will try to make this as clear as possible. I just purchased an 4700 sq ft industrial zoned building, when I tried to have the power turned on/transferred into my name the utility company said I needed a city inspection since it has been turned off for more than 12 months. The inspection is scheduled for tomorrow at noon, the inspector sounded like he was going to be a PITA. He gave me a list of what they check for, the one item he said is there must be two grounds, (1 at a ground rod and he said a cold water ground was acceptable for the second).
Here is a quick drawing of the layout:
Here is the setup:
There are a total of 3 meters (2) single phase and a three phase.
The #1 single phase load center has a ground going to the #1 cold water pipe and a ground going to the ground rod.
The #2 single phase and three phase disconnects have a ground wire running to the ground rod only.
The #1 single phase subpanel/load center, #2 single phase subpanel/load center and the three phase disconnect all have grounds running to the #2 cold water pipe.
Everything is run through metal conduit. The main water supply comes into the building right where the #1 cold water ground is.
The front part of the building was the original part, and the rear was added on later, there is no seperation between the buildings, they share the dividing wall.
The 1st single phase meter/subpanel clearly has 2 grounds, so I know I am fine on that. Both grounds are bonded on a ground bar in the load center.
My concern is the 2nd single phase meter/disconnect and the 3 phase meter/disconnect. The 2nd ground is tied in at 2 sources, through the conduit to the #2 cold water from the subpanels. It also would pull a ground to the #1 cold water from the wire running from the ground rod to the #1 single phase panel, since it is connected with the cold water ground on the ground bar in that panel. I just don't know if that is an acceptable ground code. Does anyone know? If so, do you know the section of NEC I could reference to argue my point if it gets questioned?
Everything looks like it was professionaly installed by electricians, so I don't want to mess with it, unless necessary. Even if there isn't 2 acceptable grounds, isn't existing construction grandfathered in? I do not plan on doing any new electrical work at all, the permit was only pulled as a requirement to get the inspection to have the power turned on. The building is in Cleveland, OH if it makes a difference.
Thanks
Here is a quick drawing of the layout:
Here is the setup:
There are a total of 3 meters (2) single phase and a three phase.
The #1 single phase load center has a ground going to the #1 cold water pipe and a ground going to the ground rod.
The #2 single phase and three phase disconnects have a ground wire running to the ground rod only.
The #1 single phase subpanel/load center, #2 single phase subpanel/load center and the three phase disconnect all have grounds running to the #2 cold water pipe.
Everything is run through metal conduit. The main water supply comes into the building right where the #1 cold water ground is.
The front part of the building was the original part, and the rear was added on later, there is no seperation between the buildings, they share the dividing wall.
The 1st single phase meter/subpanel clearly has 2 grounds, so I know I am fine on that. Both grounds are bonded on a ground bar in the load center.
My concern is the 2nd single phase meter/disconnect and the 3 phase meter/disconnect. The 2nd ground is tied in at 2 sources, through the conduit to the #2 cold water from the subpanels. It also would pull a ground to the #1 cold water from the wire running from the ground rod to the #1 single phase panel, since it is connected with the cold water ground on the ground bar in that panel. I just don't know if that is an acceptable ground code. Does anyone know? If so, do you know the section of NEC I could reference to argue my point if it gets questioned?
Everything looks like it was professionaly installed by electricians, so I don't want to mess with it, unless necessary. Even if there isn't 2 acceptable grounds, isn't existing construction grandfathered in? I do not plan on doing any new electrical work at all, the permit was only pulled as a requirement to get the inspection to have the power turned on. The building is in Cleveland, OH if it makes a difference.
Thanks