Attached structures with 2 lines back to meter?

chedv

Member
Joined
Dec 22, 2018
Messages
22
Location
Illinois
Current shed has a 3 wire subpanel fed from a 100 amp breaker at the meter/combo box. Bonding screw installed. I do not see a ground bar at this panel.

New shed is attached to the current shed. The meter is actually closer to this new shed, so we plan to run 4 wire to the meter/combo box with another 100 amp breaker. UFER has been embedded in foundation. (If needed)

Is there a problem with attached structures with separate feeds from the meter? Thanks.
 
Last edited:
To avoid these ads, REGISTER NOW!
OP
C

chedv

Member
Joined
Dec 22, 2018
Messages
22
Location
Illinois
If two feeds were used, would this cause a grounding or current issue?

Or is it more of the hazard when working on a circuit, one might not be aware of which panel it’s coming from?
 

mike93lx

ALLIANCE MEMBER
Joined
Dec 9, 2013
Messages
37,723
Location
Richmond, VA
If two feeds were used, would this cause a grounding or current issue?

Or is it more of the hazard when working on a circuit, one might not be aware of which panel it’s coming from?
The latter.

Just run a new feed, then convert the existing panel to a sub, fed from the new one.

Gives you a chance to get the existing panel upgraded to a 4 wire also
 

wyliesdiesels

Well-known member
Joined
Aug 14, 2012
Messages
20,038
Location
Modesto, CA
Current shed has a 3 wire subpanel fed from a 100 amp breaker at the meter/combo box. Bonding screw installed. I do not see a ground bar at this panel.

New shed is attached to the current shed. The meter is actually closer to this new shed, so we plan to run 4 wire to the meter/combo box with another 100 amp breaker. UFER has been embedded in foundation. (If needed)

Is there a problem with attached structures with separate feeds from the meter? Thanks.
Where is the meter main located at? On the house or a pole?
 
OP
C

chedv

Member
Joined
Dec 22, 2018
Messages
22
Location
Illinois
Meter is on a pole. Farm location. Main feed through lugs run to the house. Then a 100 amp breaker runs to existing shed.
 
To avoid these ads, REGISTER NOW!

wyliesdiesels

Well-known member
Joined
Aug 14, 2012
Messages
20,038
Location
Modesto, CA
Meter is on a pole. Farm location. Main feed through lugs run to the house. Then a 100 amp breaker runs to existing shed.
ok so of you run another feed from the meter it wont be code permitted. as previously said you can only have one feed to a structure.
 