Current shed has a 3 wire subpanel fed from a 100 amp breaker at the meter/combo box. Bonding screw installed. I do not see a ground bar at this panel.
New shed is attached to the current shed. The meter is actually closer to this new shed, so we plan to run 4 wire to the meter/combo box with another 100 amp breaker. UFER has been embedded in foundation. (If needed)
Is there a problem with attached structures with separate feeds from the meter? Thanks.
New shed is attached to the current shed. The meter is actually closer to this new shed, so we plan to run 4 wire to the meter/combo box with another 100 amp breaker. UFER has been embedded in foundation. (If needed)
Is there a problem with attached structures with separate feeds from the meter? Thanks.
Last edited: