Graham08
Well-known member
I finally get my own build thread!
I'm in the process of building a new shop in my backyard to give my metalworking equipment and racecar a new place to live (and me some room to work!), and make the attached garage back into parking.
The overall size is 36' x 48', with a 12' x 48' covered "party porch". The porch was my wife's idea, but it has turned out to be a good one, even though it has been a bunch of extra work. The finished ceiling will be right at 13'. We framed 12' tall walls, which stand on the block foundation, which has about 1-1/2 block exposed above the finished floor.
A lot of the work has been done by my dad, father-in-law, my friends, and myself on the weekends and evenings. I hired out the concrete (I've never even poured a sidewalk!) and setting the trusses and sheathing the roof. The plan is to do pretty much the rest ourselves, except for garage doors.
Here's the start...excavating! My concrete guy excavated the footers and the subgrade.
The clay here ***** for drainage, but makes a great base for a building. I was surprised that all of the excavation was done with the mini excavator.
Here are a couple shots of the block work and subgrade. There are six courses of block on top of the footer, which is 24" wide by 12" thick, with 5/8" rebar.
This was before we raised the grade another 6" or so. There was a miscommunication that resulted in the finished floor being lower than the surrounding grade. I chose to spend the extra few bucks on gravel instead of fighting to keep water out for eternity!
Part of the new shop is an electrical upgrade for the property. We're going to 400 amp service, with a remote meter pedestal, so I can have 200 amp panels in the shop and the house. My father-in-law is a retired electrician, and he was a huge help in planning the job (new service cable for the shop and the house) and actually doing the work. The new meter base is part of his handywork.
Here are a few pictures of the concrete guys doing their thing. The slab is 5" thick, over top of 2" rigid foam. My last shop had the foam under the floor, and it makes a huge difference in heating the building, as well as keeping the floor from sweating in the humid Ohio summers.
And the finished floor...
I'm in the process of building a new shop in my backyard to give my metalworking equipment and racecar a new place to live (and me some room to work!), and make the attached garage back into parking.
The overall size is 36' x 48', with a 12' x 48' covered "party porch". The porch was my wife's idea, but it has turned out to be a good one, even though it has been a bunch of extra work. The finished ceiling will be right at 13'. We framed 12' tall walls, which stand on the block foundation, which has about 1-1/2 block exposed above the finished floor.
A lot of the work has been done by my dad, father-in-law, my friends, and myself on the weekends and evenings. I hired out the concrete (I've never even poured a sidewalk!) and setting the trusses and sheathing the roof. The plan is to do pretty much the rest ourselves, except for garage doors.
Here's the start...excavating! My concrete guy excavated the footers and the subgrade.
The clay here ***** for drainage, but makes a great base for a building. I was surprised that all of the excavation was done with the mini excavator.
Here are a couple shots of the block work and subgrade. There are six courses of block on top of the footer, which is 24" wide by 12" thick, with 5/8" rebar.
This was before we raised the grade another 6" or so. There was a miscommunication that resulted in the finished floor being lower than the surrounding grade. I chose to spend the extra few bucks on gravel instead of fighting to keep water out for eternity!
Part of the new shop is an electrical upgrade for the property. We're going to 400 amp service, with a remote meter pedestal, so I can have 200 amp panels in the shop and the house. My father-in-law is a retired electrician, and he was a huge help in planning the job (new service cable for the shop and the house) and actually doing the work. The new meter base is part of his handywork.
Here are a few pictures of the concrete guys doing their thing. The slab is 5" thick, over top of 2" rigid foam. My last shop had the foam under the floor, and it makes a huge difference in heating the building, as well as keeping the floor from sweating in the humid Ohio summers.
And the finished floor...
Last edited:
.