Biggest slab size with radiant heat

Cd_r3105

Member
Joined
Jul 26, 2022
Messages
11
I'm building a detached garage with a radiant heat floor, and currently deciding on the design of it. Initially I was thinking of pouring 8" of concrete on top of 2-inch 25-psi insulation foam boards, with reinforced steel mesh and chairs to lift the PEX about 2 inch up from the boards.
However, I'm thinking that with that design, the room would take too much time to heat up and 8" might not be supported by the foam boards anyway. I'm now thinking of pouring 2 layers of concrete (3" and 5" or 4" and 4") and sandwich the insulation boards in-between with the mesh and chairs on the upper concrete layer. What do the experts here think?
 
To avoid these ads, REGISTER NOW!

benwah

Well-known member
Joined
May 21, 2014
Messages
985
Location
Lakewood, Colorado
Here in Gunnison County concrete is typically poured 4"-5" thick over 2" Polystyrene board, then mesh, then the PEX is tied to the mesh, then rebar is layerd over. IDK how other parts of the country do it, but this is how most of us do it.
 

Attachments

  • IMG_20170512_073508155.jpg
    IMG_20170512_073508155.jpg
    576.8 KB · Views: 61

ConCretin

Well-known member
Joined
Jan 20, 2011
Messages
3,381
Location
Central Maine
With all due respect, your plan seems unnecessarily complicated and expensive. Four or five inches or concrete is more than adequate for all but the heaviest loads and two placements will add to the time and expense. If it's a mono slab you can just thicken the edge to support building loads.

I prefer to staple the PEX to the rigid board insulation and support my reinforcing above it. You could install a layer of cheap mesh first and tie the PEX to it if you want to get it a little higher in the slab.

You want your reinforcing as high as possible without risking interference when cutting your control joints and you definitely want your PEX out of harms way. I've found this approach works best to accomplish both goals.

Give my Guide to Floor Slabs in the link below a read for some additional thoughts. Good luck and congrats on the new shop!
 
OP
C

Cd_r3105

Member
Joined
Jul 26, 2022
Messages
11
Thanks for your comment. The heaviest load for my would be my Toyota tundra or similar kind of truck, 5,480 lbs. Did you mean to include a link?
 

ConCretin

Well-known member
Joined
Jan 20, 2011
Messages
3,381
Location
Central Maine
Thanks for your comment. The heaviest load for my would be my Toyota tundra or similar kind of truck, 5,480 lbs. Did you mean to include a link?
There's a link in my signature line. It's titled "The Concrete Underground Guide to Floor Slabs".

A slab on grade can span short distances and 'spread the load' but it isn't really structural and depends on the ground below to support the loads placed on it. A four inch slab on a solid base is absolutely fine for vehicular loads. With that said, it's not very costly to thicken it an inch for insurance, a possible lift or just to fit everything in. It can get a little congested with radiant especially if you want some extra concrete under the PEX.
 

haugy

Well-known member
Joined
Dec 1, 2009
Messages
783
Location
Nashville, TN
I did a 6" slab on mine. 15 mil vapor barrier, then foam board underneath. I put my #4 rebar on 1.5" chairs so with the rebar and chairs the top of rebar was about 2" into slab. I then tied my pex to the rebar. I have safely 2.5"+ below the top of my slab before I get to pex. My 6" slab is more than enough for most loads, including a fork lift and heavy trucks (empty) as well as for a 2-post lift.

It's your shop, but 8" is major thick, and if you put your pex at the bottom of that, you'll never get the benefit of the heat in my opinion. Some places you can call and they'll configure your layout and depths of pex for you based on your design and need.
 

Attachments

  • IMG_3387.jpg
    IMG_3387.jpg
    164.1 KB · Views: 49
  • IMG_3390.jpg
    IMG_3390.jpg
    182.2 KB · Views: 44
  • IMG_3391.jpg
    IMG_3391.jpg
    187 KB · Views: 44
To avoid these ads, REGISTER NOW!

Snowfighter

New member
Joined
Jul 28, 2022
Messages
4
I’ve done all my houses and garages with radiant heat my current new garage/car shop pics are attached 5” of concrete is plenty. It all falls back to your sub base. The concrete will only be as strong as what is supporting it.02BC46C8-5471-433B-8EC8-17F9B407B888.jpeg5C2CFA8B-A9D6-4352-AF61-9BDCB964A056.jpegDB6111FC-212A-4EF0-B95E-1B1D5193763C.jpeg18F37501-C0A1-49BC-9EA2-47F61B94BEC5.jpegF461CA21-61C2-476E-9CC6-9607D71FBC94.jpeg
 

haugy

Well-known member
Joined
Dec 1, 2009
Messages
783
Location
Nashville, TN
You clearly do not understand the way radiant heat works.....
Neither do you apparently.

There are too many variables we don't know. Floor size, will the building be insulated, will it be heated as well? What size pex is he going with? What size boiler and pumps?

I said he won't get the benefit. The benefit being a heated floor to either maintain a shop temperature above freezing, or have on demand heat at your desired level. At 8" thick, he'd have to have very large pex and boilers to get that thing up to temperature in a day. So he either knows exactly when he'll be out there, or he'll have to leave it on all the time. At which point that becomes very inefficient at those oversized numbers.

Again too many unknowns. So go ahead and tell me I don't know. That's fine. There's a million ways to skin this cat. I look at it in terms of functionality, efficiency, and simplicity. Sure you can make 8" heated. But it'll cost you. In terms of money, time, and effectiveness.
 
Last edited:

SBAG

Well-known member
Joined
Aug 27, 2022
Messages
208
I went with (36x48 ft - still in progress) of 2 in foam, pex stapled to the foam, fiberglass rebar on chairs, and six inches of concrete. I definitely wanted the pex stapled to the foam and my installer was in agreement. This lets you drill in maybe 3-4 inches without worrying about hitting a pipe.
 

Attachments

  • image_50407425.JPG
    image_50407425.JPG
    578.7 KB · Views: 30
  • image_16898561.JPG
    image_16898561.JPG
    785.3 KB · Views: 39

jblnut

ALLIANCE MEMBER
Joined
Jan 17, 2015
Messages
7,237
Location
In the Middle of MN
Neither do you apparently.

There are too many variables we don't know. Floor size, will the building be insulated, will it be heated as well? What size pex is he going with? What size boiler and pumps?

I said he won't get the benefit. The benefit being a heated floor to either maintain a shop temperature above freezing, or have on demand heat at your desired level. At 8" thick, he'd have to have very large pex and boilers to get that thing up to temperature in a day. So he either knows exactly when he'll be out there, or he'll have to leave it on all the time. At which point that becomes very inefficient at those oversized numbers.

Again too many unknowns. So go ahead and tell me I don't know. That's fine. There's a million ways to skin this cat. I look at it in terms of functionality, efficiency, and simplicity. Sure you can make 8" heated. But it'll cost you. In terms of money, time, and effectiveness.
Isn't one of the largest benefits of in floor radiant heat to be consistent heat throughout the space ? Leaving it on all the time is sort of a requirement for that. It sounds like the OP is wanting to vary the temp based on "the room would take too much time to heat up" so let's ask the questions you don't know the answers to.

Hey OP !!! Do you intend to only turn the heat on when you plan to work out there or leave it on all the time ?

I have a 54x72x18 farm shop with a strong 6" of concrete and I leave the heat on all the time. We frequently have gatherings in there over winter and if I raise the temp from 58f to 67f it will heat up in 12hrs. My 120k btu boiler ***** the propane down like crazy the entire time but it responds fairly quickly.

OP if you do intend to leave the heat on all the time and aren't afraid of the added expense of all that goes with in floor heat I'd say go for it. Even if you want to pour 8" of mud in true GJ overkill fashion it'll work just fine. It just won't be as responsive if you want to change the temp in a matter of hours. If you ever purchase a payloader or want to back a fully loaded gravel truck in there you'd be covered and won't fall through the floor lol
 

TractorJeff

Well-known member
Joined
Dec 8, 2013
Messages
3,309
Location
Elkhorn, WI
I sometimes have 3 Bulldozers up to CAT D6 size in my Shop at one time for Service on 6 inches of Concrete.
Never Cracked! It's all in the Base!
 