First garage build in 40+ years. Things have changed a bit since I "winged it" back then.
Trusses are up, plumbed and spaced as closely as they're going to be. I've finished installing 2x6 sub-facia and will finish 1x8 facia today. I'm thinking about next steps in the build so I've thrown together a sequence list as best I understand the steps.
Thanks, Tim
Trusses are up, plumbed and spaced as closely as they're going to be. I've finished installing 2x6 sub-facia and will finish 1x8 facia today. I'm thinking about next steps in the build so I've thrown together a sequence list as best I understand the steps.
- Sheathing the roof. I'll add some stop blocks along the eves to help keep the sheathing aligned with them. I'm comfortable with the process of sheathing the roof. Leaving ridge vent gap along peak.
- Ice/water barrier along eves
- Felt/underlayment/whatever you call it next. Stapled down on the sheathing.
- Aluminum drip edge all around the edges.
- Starter shingles along eves
- Shingle roof. Add ridge vent and shingle over them.
- Fit aluminum soffit and facia.
Thanks, Tim