So I am planning on pouring concrete floor with radiant floor heating and a car lift for my shop with a footing this summer and I just wanted to get some opinions and help on this setup:
Shop is 32’wx30’ long with existing perimeter footing and a center run footing down the length.
This setup is for one half of my shop where the lift will reside.
Bendpak 10AP-168 2 post lift
Rebar reinforced existing Footings are 20” wide, 8” thick.
Inbetween existing footing
26.5 ft long
13.5 ft wide
Lift 145” wide
Lift base plates is going to be 7 inch away from side footings and it’ll be centered in the 26.5’ length.
I will be running radiant heat lines ontop of 2.5” 16psi grid foam (hydropex) under the slab with 4.5” thick concrete and not running any on the 4’x13.5’ section the lift will be on that will be 7” thick concrete as the absence of foam under that pad.
For rebar in the lift pad is 0.5” rebar in a 1 foot grid the size of the lift pad good? And should I run more rebar down the length of the slab too?
Also thinking of tying the new pour into the existing footing with rebar, what would be the best way for this? (Depth of tie in, how much to stick out into new pour, how many feet interval)
Also is keying in under the existing footing necessary? Bendpak says to do so when cuting out a section of old concrete to pour a base for the lift but im just thinking as my base is pretty narrow but a long slab is it neccessary in my case?
Thanks for any help and suggestions!
Shop is 32’wx30’ long with existing perimeter footing and a center run footing down the length.
This setup is for one half of my shop where the lift will reside.
Bendpak 10AP-168 2 post lift
Rebar reinforced existing Footings are 20” wide, 8” thick.
Inbetween existing footing
26.5 ft long
13.5 ft wide
Lift 145” wide
Lift base plates is going to be 7 inch away from side footings and it’ll be centered in the 26.5’ length.
I will be running radiant heat lines ontop of 2.5” 16psi grid foam (hydropex) under the slab with 4.5” thick concrete and not running any on the 4’x13.5’ section the lift will be on that will be 7” thick concrete as the absence of foam under that pad.
For rebar in the lift pad is 0.5” rebar in a 1 foot grid the size of the lift pad good? And should I run more rebar down the length of the slab too?
Also thinking of tying the new pour into the existing footing with rebar, what would be the best way for this? (Depth of tie in, how much to stick out into new pour, how many feet interval)
Also is keying in under the existing footing necessary? Bendpak says to do so when cuting out a section of old concrete to pour a base for the lift but im just thinking as my base is pretty narrow but a long slab is it neccessary in my case?
Thanks for any help and suggestions!
