Well, since the garage addition built on the street-side of the house didn't go over with the landlord, he suggested that I do some research on a metal out-building for placement on the side of the house (which is the back in relation to my entrance door).
So here's the deal. To deliver and set up an 18x21 foot metal building on the ground is roughly $2500.00.
I'm thinking of sinking 4x4 treated posts into the ground with another 4x4 atop of the posts for the foundation around the parimeter of the building. More post and beams down the center of the structure, then cross members for support of the partial wooden floor. The floor would be an "L" shape running the length of one 21' side and also along the back wall for a washer and dryer and whatever else. (workbench, shelves?) Parking will be on the gravel floor on the other half of the building.
Then there's insulating the whole thing, running electrical (outlets and lights) plumbing, etc. (plumbing and electric access is only a few feet away).
If I did all the work myself, including renting a skid steer ($259.00 a day) to prep for gravel, how much over the $2500.00 for the building is this going to cost in materials. The new driveway is approximately 75'. I guesstimated the whole shebang would be about $5000.00. How close do you think I am?
Much oblidged for the insight...
Bill
So here's the deal. To deliver and set up an 18x21 foot metal building on the ground is roughly $2500.00.
I'm thinking of sinking 4x4 treated posts into the ground with another 4x4 atop of the posts for the foundation around the parimeter of the building. More post and beams down the center of the structure, then cross members for support of the partial wooden floor. The floor would be an "L" shape running the length of one 21' side and also along the back wall for a washer and dryer and whatever else. (workbench, shelves?) Parking will be on the gravel floor on the other half of the building.
Then there's insulating the whole thing, running electrical (outlets and lights) plumbing, etc. (plumbing and electric access is only a few feet away).
If I did all the work myself, including renting a skid steer ($259.00 a day) to prep for gravel, how much over the $2500.00 for the building is this going to cost in materials. The new driveway is approximately 75'. I guesstimated the whole shebang would be about $5000.00. How close do you think I am?
Much oblidged for the insight...