Ok, I'm sure this has been asked before, but I can't seem to find the thread.
I am getting so close to move in day on my new shop, I can taste it. Only a couple of big projects left to go.
(Not listed in any particular order)
1. Epoxy the floor
2. Drywall/Paint
3. Install radiant heat hardware (boiler, pump, etc)
4. Trim out the electrical
Here's the rub... I've been waiting on my heat source for almost a month. It's going to be at least another week until it shows up. I can hang a couple of sheets of drywall where the boiler package mounts, then finish the rest of the drywall later.
I've got a big pile of boxes of epoxy (Rustoleum Pro) just waiting to go on the floor. While waiting for the heat source, I've knocked out all the prep work, and the floor is ready to coat. I'm planning a base coat, top coat, flakes and then clear coat. I could start RIGHT NOW.
Well, except for this little detail... I'm worried about the weather, mainly the temp. I'm in the Seattle area, and it's getting on with early winter conditions here. High temps for the next few days are 45 degrees, with lows near freezing. No rain in the forecast, but it's always humid. The building is fairly well insulated, but there won't be any heat available if I do the floor now.
Question is this... Would I be stupid to go ahead with this? I have enough time this week to do one coat, wait 24 hours for the next, and another 24 hours for the clear. I would be done by Friday night.
My heat source should be here by the middle of next week. If I wait for that, I may get it installed and running by the end of the week, then try to coat the following week. That pushes the floor back by two weeks.
This is driving me nuts! I've got this beautiful building sitting out there and I can't go play in it!!!
I am getting so close to move in day on my new shop, I can taste it. Only a couple of big projects left to go.
(Not listed in any particular order)
1. Epoxy the floor
2. Drywall/Paint
3. Install radiant heat hardware (boiler, pump, etc)
4. Trim out the electrical
Here's the rub... I've been waiting on my heat source for almost a month. It's going to be at least another week until it shows up. I can hang a couple of sheets of drywall where the boiler package mounts, then finish the rest of the drywall later.
I've got a big pile of boxes of epoxy (Rustoleum Pro) just waiting to go on the floor. While waiting for the heat source, I've knocked out all the prep work, and the floor is ready to coat. I'm planning a base coat, top coat, flakes and then clear coat. I could start RIGHT NOW.
Well, except for this little detail... I'm worried about the weather, mainly the temp. I'm in the Seattle area, and it's getting on with early winter conditions here. High temps for the next few days are 45 degrees, with lows near freezing. No rain in the forecast, but it's always humid. The building is fairly well insulated, but there won't be any heat available if I do the floor now.
Question is this... Would I be stupid to go ahead with this? I have enough time this week to do one coat, wait 24 hours for the next, and another 24 hours for the clear. I would be done by Friday night.
My heat source should be here by the middle of next week. If I wait for that, I may get it installed and running by the end of the week, then try to coat the following week. That pushes the floor back by two weeks.
This is driving me nuts! I've got this beautiful building sitting out there and I can't go play in it!!!
