River Runner
Well-known member
Good Day,
After missing out on concrete last year due to supply issues and weather I finally got my 40x64 shop floor poured a week ago. While I am not a dedicated concrete guy I have poured dozens of slabs and they usually turn out pretty decent but maybe not perfect. Because this was a big pour I had two other contractors and their crew with me along with a 35 year finisher to run the power trowel. I was feeling very confident with all the man power and experience I had at my disposal.
Everything was great until it wasn't. It was 10 am and 40 degrees outside and we were using a 6 bag mix with 3/8" aggregate. I informed the batch plant that we would be pumping the mud because we didn't think a truck could fit into the shop. The mix was as requested by the pumper.
We had immediate clogging right away and spent the first hour breaking hoses and trying to deal with the mud not pumping. After an hour of only pumping about a yard I rejected the truck and told the pumper to clean up. At this point the 2nd truck was already on site. I thought about calling the whole thing off but I knew that it would be months or longer before I could get scheduled again. I noticed that the 2nd truck was shorter than the other and we were able to back the truck in with about 2" of clearance, so we just started raking like dogs as we had the man power. From that point on the job went smooth and we had all 5 trucks dumped in a few hours. The batch plant is only about 1/2 a mile away so waiting between trucks was minimal.
After we had let the mud set up we started working it. I noticed right away that it was incredibly sticky. So sticky that when I went out on my skates I would get stuck and the cream would tear from the surface. The mud also never really had any bleed water, which I have not seen before. So, we busted out the power trowel and every time we tried to spin the blades it would kill the engine because it was so sticky. We finally got it going and didn't dare turn it off out of fear we couldn't get it moving again.
The mud that the 2nd truck dumped was not setting so we had to work around it. After a while I started to notice blistering on the surface on the last pass with the trowel. My finisher said it was the worst mud he has seen in 35 years of finishing concrete and that it was loaded with air. The mud from the 2nd truck was still not setting after finishing all the rest. Eventually we called it at 1 am because all it would do is smear across the surface of the adjacent set concrete, basically looking like troweled drywall mud with a skipped trowel finish.
I know that blistering occurs when you finish it too soon while its still bleeding air and water but I can tell you that was not the case. The surface was getting so stiff that we couldn't even mag it, there was so little cream and again, it was incredibly sticky. Its been a little over a week and the surface *****. Blisters all over the slab and a wavy surface in the area that wouldn't set up.
I have since spoken to the batch plant and expressed my disapproval with regards to the mud. They have however already charged my credit card and I also have the bill from the pumper. I am hoping to at best get my money back from them for the mud. It was record high cost, $229 a yard! I have a $4,000 40' trench drain in the shop and the slab is 6" thick with #4 rebar.
I'm not sure where to go from here as I have never had a pour go bad. I can chip out the blisters by smacking them with a hammer leaving a 1/8" - 1/4" deep crater. I think my only option at this point is to grind the whole surface down 1/4" and resurface? Because of my drain I can't really take off material without adding something. The floor will be subject to all sorts of abuse ranging from copious amounts of water from a bridge saw, sparks from welding, heavy traffic from a skid steer and fluids from vehicles, its my do all shop.
I am thinking I can gain the 1/4" height back by tiling the whole shop with a porcelain tile. I am looking for ideas on ways to polish the expensive turd surface that I will have. I can't really do a full overlay as it will mess up my header heights for the doors. The shop has block walls so I am not about to change the header height.
I've also looked at the Supratiles and they seem like a good option but may not hold up to sparks or molten metal from cutting and welding?
All the options seem to be about as expensive as the concrete itself was but the thought of tearing out 46 yards of concrete with rebar seems awful. Hopefully I can get Knife River to own up to crappy mud and share some expense on a repair option. Sorry for the novel but I don't have experience resurfacing a concrete floor subject to shop use. Thanks!
After missing out on concrete last year due to supply issues and weather I finally got my 40x64 shop floor poured a week ago. While I am not a dedicated concrete guy I have poured dozens of slabs and they usually turn out pretty decent but maybe not perfect. Because this was a big pour I had two other contractors and their crew with me along with a 35 year finisher to run the power trowel. I was feeling very confident with all the man power and experience I had at my disposal.
Everything was great until it wasn't. It was 10 am and 40 degrees outside and we were using a 6 bag mix with 3/8" aggregate. I informed the batch plant that we would be pumping the mud because we didn't think a truck could fit into the shop. The mix was as requested by the pumper.
We had immediate clogging right away and spent the first hour breaking hoses and trying to deal with the mud not pumping. After an hour of only pumping about a yard I rejected the truck and told the pumper to clean up. At this point the 2nd truck was already on site. I thought about calling the whole thing off but I knew that it would be months or longer before I could get scheduled again. I noticed that the 2nd truck was shorter than the other and we were able to back the truck in with about 2" of clearance, so we just started raking like dogs as we had the man power. From that point on the job went smooth and we had all 5 trucks dumped in a few hours. The batch plant is only about 1/2 a mile away so waiting between trucks was minimal.
After we had let the mud set up we started working it. I noticed right away that it was incredibly sticky. So sticky that when I went out on my skates I would get stuck and the cream would tear from the surface. The mud also never really had any bleed water, which I have not seen before. So, we busted out the power trowel and every time we tried to spin the blades it would kill the engine because it was so sticky. We finally got it going and didn't dare turn it off out of fear we couldn't get it moving again.
The mud that the 2nd truck dumped was not setting so we had to work around it. After a while I started to notice blistering on the surface on the last pass with the trowel. My finisher said it was the worst mud he has seen in 35 years of finishing concrete and that it was loaded with air. The mud from the 2nd truck was still not setting after finishing all the rest. Eventually we called it at 1 am because all it would do is smear across the surface of the adjacent set concrete, basically looking like troweled drywall mud with a skipped trowel finish.
I know that blistering occurs when you finish it too soon while its still bleeding air and water but I can tell you that was not the case. The surface was getting so stiff that we couldn't even mag it, there was so little cream and again, it was incredibly sticky. Its been a little over a week and the surface *****. Blisters all over the slab and a wavy surface in the area that wouldn't set up.
I have since spoken to the batch plant and expressed my disapproval with regards to the mud. They have however already charged my credit card and I also have the bill from the pumper. I am hoping to at best get my money back from them for the mud. It was record high cost, $229 a yard! I have a $4,000 40' trench drain in the shop and the slab is 6" thick with #4 rebar.
I'm not sure where to go from here as I have never had a pour go bad. I can chip out the blisters by smacking them with a hammer leaving a 1/8" - 1/4" deep crater. I think my only option at this point is to grind the whole surface down 1/4" and resurface? Because of my drain I can't really take off material without adding something. The floor will be subject to all sorts of abuse ranging from copious amounts of water from a bridge saw, sparks from welding, heavy traffic from a skid steer and fluids from vehicles, its my do all shop.
I am thinking I can gain the 1/4" height back by tiling the whole shop with a porcelain tile. I am looking for ideas on ways to polish the expensive turd surface that I will have. I can't really do a full overlay as it will mess up my header heights for the doors. The shop has block walls so I am not about to change the header height.
I've also looked at the Supratiles and they seem like a good option but may not hold up to sparks or molten metal from cutting and welding?
All the options seem to be about as expensive as the concrete itself was but the thought of tearing out 46 yards of concrete with rebar seems awful. Hopefully I can get Knife River to own up to crappy mud and share some expense on a repair option. Sorry for the novel but I don't have experience resurfacing a concrete floor subject to shop use. Thanks!
