Well-known member
My concrete contractor wants to pour the slab for my barn in two pours. I'm all in on the idea as it gives them more time to do a good job without rushing to do the entire slab in one day.
The contractor suggested using a keyway at the slab to slab joint. I've done some research and created the sheet shown below.
Questions:
Slab Data:
Thanks for your input.
The contractor suggested using a keyway at the slab to slab joint. I've done some research and created the sheet shown below.
Questions:
- In your experience is a keyway a good option?
- How long should I request they wait before the first pour and the second pour?
Slab Data:
- 5" thick
- 4,000 PSI Concrete
- Angel Hair Fiber
- 6 x 6-W2.9 x W2.9 Wire Mesh installed on 2" concrete dobies spaced on 24" center to center.
Thanks for your input.